- 00:02:40: Meeting Commences: Roll Call and Minute Approval
- 00:05:17: Harpoon Brewery Outdoor Hospitality License Agreement Renewal
- 00:07:44: Massport Wayfinding Signage Installation License Agreement
- 00:11:15: Transportation Department Lease Extension at 12 Channel
- 00:13:07: Blackbod Accounting System Contract Renewal Authorization
- 00:14:43: 12 Channel Canopy Repair Contract Amendment Authorization
- 00:18:16: Personnel Changes and Collective Bargaining Agreement Approval
- 00:21:12: Redevelopment Authority Board Meeting Commences
- 00:22:36: City Councilor Durkin Voices Project Support
- 00:27:21: Approval of April 16th Minutes and Public Hearing Schedule
- 00:29:54: Applications For MassWorks and Housing Works Programs
- 00:32:23: Placemaking Activation Events on Winter Street and Chinatown
- 00:42:13: Long Wharf Informational Kiosk: Sea Level Rise Awareness
- 00:45:01: Long Wharf Parking License Agreement Amendment Approval
- 00:47:42: Charlestown Navy Yard Lease Assignment to USS Constitution
- 00:50:55: Washington Park Urban Renewal Projects: Designations Extension
- 00:55:06: Welcome Home Boston: Project Designation Status Awards
- 01:11:32: Stewart Street Parcel Taking and Deed Execution Approval
- 01:14:32: Chinatown Zoning Update and Design Guidelines Approval
- 01:35:29: Citywide Zoning Signage Regulations Implementation
- 01:48:44: Approval of Certificate of Completion for Columbus Owner LLC
- 01:49:16: Certificate of Completion for 200 Cort Boulevard Project
- 01:49:47: Certificate of Completion for Parcel J-1 Milk Street
- 01:50:35: Waiver and Project Changes at 90 Braintree Street
- 01:51:41: Presentation: Proposed Changes at 90 Braintree Street
- 01:54:24: Approval and 419 Boylston Street Conversion Program
- 01:55:29: Presentation: 419 Boylston Street Conversion Program
- 01:58:14: Board Questions and Comments: 419 Boylston Conversion
- 02:00:17: Contractor responsibility and motion to move forward
- 02:01:03: Approval and Brief Recess Announcement
- 02:12:46: Public Hearing: Bartlett Place Phase 2 Building C
- 02:15:13: Presentation: Bartlett Place Phase 2 Building C
- 02:25:37: Public Testimony and Union Support for Project
- 02:27:08: Board Questions: Affordability and Sustainability Concerns
- 02:29:16: Continued conversation: PV and motion to move forward
- 02:30:14: Public Hearing: West End Library Redevelopment
- 02:33:15: Presentation: West End Library Redevelopment Project
- 02:41:24: Representative and Councilor support for Project
- 02:43:35: Affordable Housing Overview and Design Strategy
- 02:52:01: Continued city partnership and presentation conclusions
- 02:52:18: Public Testimony Begins: Support for the Redevelopment
- 03:01:04: Public Testimony Continued: Union Support and Concerns
- 03:01:25: Public Testimony Continued: Civic support with negative comments
- 03:03:54: Public Testimony Concluded: Arguments Opposing Project
- 03:08:06: Board Comments: Excitement for Affordable Housing
- 03:09:39: More discussion: Details and final questions
- 03:12:10: Approval and 50 Congress Street Conversion Program
- 03:13:15: Presentation: 50 Congress Street Conversion Program
- 03:17:11: Board Approval
- 03:17:58: 1 State Street Conversion Program Discussion
- 03:18:49: Presentation: 1 State Street Conversion Program
- 03:22:16: Approval and 320 Summer Street Conversion Program
- 03:23:48: Presentation: 320 Summer Street Conversion Program
- 03:27:51: Board Conversation About Potential Project Ceasing
- 03:31:04: Final Thoughts and Approval
- 03:31:28: Contractual Payments and Personal items
- 03:32:34: Director Shen's Report: Approvals and Achievements


Part: 1

1
00:02:40.000 --> 00:03:05.200
Afternoon. My name is Raheem Shepard. I am vice chair of the BPDA board sitting in for chair Rojas who will join us part of the meeting. Thank you for joining the May 14th, 2026

2
00:03:05.200 --> 00:03:22.959
Economic Development and Industrial Corporation of Boston board meeting. At this time, the Boston Planning and Development Agency is hosting public meetings in a hybrid setting for the health, safety, and accessibility of Boston residents. Hybrid means that our

3
00:03:22.959 --> 00:03:39.920
board meetings are conducted in person at city hall in our boardroom on the ninth floor and virtually via Zoom and Boston CityTV. For more information and updates, visit bostonplans.org. The open public meeting law requires

4
00:03:39.920 --> 00:03:57.439
that I notify the public that this meeting is being recorded. Please be aware that an audio and visual recording of this meeting is being made and broadcast by Boston City TV, which is part of the City of Boston Office of Cable Communications at Xfinity channel

5
00:03:57.439 --> 00:04:20.040
26 RCN channel 13 and Ver Verizon Files channel 962 and livereamed at www.boston.boston.gov/cable. If there is anyone in the audience who is recording this meeting, please identify yourself now.

6
00:04:22.079 --> 00:04:39.120
With that, we will start off with a roll call. Miss Bennett >> present. >> Mr. Ali >> here. >> Not at this one. So then and chair is present. Thank you very much.

7
00:04:39.120 --> 00:04:56.080
Item number one, request authorization for the approval of the minutes of the April 16, 2026 board meeting. >> So moved. >> Second. >> There's a second. Uh, all in favor? >> I. >> Any oppose?

8
00:04:56.080 --> 00:05:17.680
Eyes have it. Item number two, request authorization to enter to a license agreement with the Mass Bay Brewing Company, Inc. for use of parcels S3 and S2 in the Raymond L. Flynn Marine

9
00:05:17.680 --> 00:05:33.840
Park to host an outdoor hospitality space and to allow hub sports Boston adult sports leagues from May 15, 2026 through December 31, 2026. Moren, >> thank you. Good afternoon, members of

10
00:05:33.840 --> 00:05:48.960
the board. Harpoon has been a tenant of the BPDA since 1987 and is located at 306 Northern Avenue in the Raymond Alflyn Marine Park. Since 2020, the BPDA board has approved annual license agreements to temporarily change the

11
00:05:48.960 --> 00:06:05.840
permitted use of parcel S3 and a portion of parcel S2 of the Harpoon leaseold area into an outdoor hospitality space as well as permitting the hosting of Hub Sports Boston adult sports leagues and pickle ball. Currently, BPDA staff has

12
00:06:05.840 --> 00:06:22.479
entered into a 30-day license agreement to assist Harpoon with with reopening the host hospitality space as soon as possible. Harpoon understands that the 30-day license shall only be extended and made operable for the terms and conditions substantially consistent with

13
00:06:22.479 --> 00:06:37.840
the board memo and term sheet included here upon board approval. The license shall commence May 15th and expire on December 31st, 2026. Fixed rent shall be calculated at 13.75% of all gross revenue collected from all

14
00:06:37.840 --> 00:06:54.560
activities on parcel S2 and S3. Additionally, during each of the Harpoon's allowed festival weekends per their lease agreement, Harpoon shall be allowed to temporarily close the hospitality space and include parcel S2 and S3 as part of the festival area.

15
00:06:54.560 --> 00:07:09.360
Harpoon will not be required to pay fixed strength of 13.75% of all gross revenue for each of the festival weekends. BPDA staff recommends that that the director be authorized to enter into a license agreement with Harpoon to operate an outdoor

16
00:07:09.360 --> 00:07:25.840
hospitality space on parcel S3 and S2 in the Raymanel Flynn Marine Park during 2026. Thank you and I'm happy to answer any questions. >> Thank you, Moren. Uh are there any questions or comments from the board? Seeing in hearing none, is there a

17
00:07:25.840 --> 00:07:44.240
motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? >> Eyes have it. Thank you again. Item number three, request authorization to enter into a license agreement with the Massachusetts

18
00:07:44.240 --> 00:07:59.440
Port Authority for use of the BPDA owned um BPDA owned sidewalks within the Raymond L. Flynn Marine Park for the installation of wavefinding signage for a period of three years

19
00:07:59.440 --> 00:08:16.319
commencing June 1st, 2026 and ending May 31st, 2029 with two one-year term renewal options. Moren, >> thank you. Several large major events have been scheduled to take place in the city of Boston in 2026, including but

20
00:08:16.319 --> 00:08:32.959
not limited to the FIFA World Cup and Seal Boston. Seal Boston will feature an international fleet of tall ships celebrating the 250th anniversary of the United States. The event is expected to draw millions of visitors to Boston. The festivities will kick off on July 11th

21
00:08:32.959 --> 00:08:49.920
with the grand parade of sale followed by free tall ship boardings and events hosted across the seapport, Boston Harbor, and the Raymond Alin Marine Park. Currently, the Rayman Alflyn Marine Park and the South Boston waterfront lack a cohesive pedestrian wayfinding system. Massport has recently

22
00:08:49.920 --> 00:09:05.519
approached BPDA staff to propose a system of stansions which will serve as wayfinding signs across the area and within the Rayman Alofflin Flynn Marine Park to direct the millions of pedestrians expected to visit the city during the 2026 events. Massport has

23
00:09:05.519 --> 00:09:21.920
proposed 20 stansions at critical pedestrian decision points with four stansions being positioned within the Rayman Flin Marine Park. One at Summer Street at dry do a one at Harbor Street at dry do a one at Harbor Street at Northern A and the fourth at Drydock A

24
00:09:21.920 --> 00:09:38.880
at design center place. All stansions and locations must be approved by BT BPDA staff and all installations maintenance and removal shall be in accordance with existing BPDA standards. Opera operationally, the city of Boston, Massport, and BPDA will benefit from the

25
00:09:38.880 --> 00:09:54.959
proposed wayfinding signs, which will assist the unexpected influx of visitors in locating local attractions, including but not limited to the Harborwalk, Manino Convention and Exhibition Center, and the Flynn Cruiseport. Massport intends to install

26
00:09:54.959 --> 00:10:10.480
and maintain at Massport sole cost and expense the stansions prior to the commencement of the large major events that is scheduled. Due to the mutually beneficial nature of the massport funded signage, no fee is proposed. The proposed license shall be for three

27
00:10:10.480 --> 00:10:27.279
years commencing on June 1st, 2026 and expiring on on May 31st, 2029 with two single additional one-year option terms that may that may be exercised at the sole discretion of the BP of the BPDA director. Staff recommends that the

28
00:10:27.279 --> 00:10:44.399
director be authorized to enter into a license agreement between the EDIC and Massport for the use of BPDA owned sidewalks within the Rayman Alflyn Marine Park for the installation of wayfinding signs. Thank you and I'm happy to answer any questions. >> Thank you. Uh this is these are two

29
00:10:44.399 --> 00:10:59.680
great things going on for the city of Boston with the anniversary of the country and the World Cup of soccer. So that's great to have um some representation in Boston. With that, are there any questions or comments from the board? Seeing and hearing none, what's the

30
00:10:59.680 --> 00:11:15.040
pleasure of the body? >> Uh, excuse me. Is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? >> Eyes have it. Thank you. Item number four, request authorization

31
00:11:15.040 --> 00:11:30.160
to extend the lease agreement with the city of Boston's transportation department to use the suite 501 at 12 channel street for a period of 5 years commencing August 1st, 2026 and ending

32
00:11:30.160 --> 00:11:46.240
July 31st, 2031 with one 5-year term renewal option. >> Moren, >> thank you. BBDA currently occupies suite 501, which is approximately 4,895 square ft of space located on the fifth

33
00:11:46.240 --> 00:12:01.680
floor of 12 Channel Street. In 2016, the BPDA board approved a 5-year lease to be used as ancillary office space. In 2021, the BPDA board approved a three-year lease extension with two one-year option terms, which are now scheduled to expire

34
00:12:01.680 --> 00:12:18.800
on July 31st, 2026. Staff is now proposing a 5-year extension that will commence on August 1st, 2026 and expire on July 31st, 2031 with one 5-year option term that may be exercised at the sole discretion of the BPDA director.

35
00:12:18.800 --> 00:12:33.920
Due to the public service nature of this occupancy, no license fee is being proposed. However, BTD pays ever source for all electricity used in the suite. Staff is recommending that the director be authorized to enter into the license agreement, the lease agreement, excuse

36
00:12:33.920 --> 00:12:50.639
me, with BTD for sweet 501 at 12 Channel Street for a 5-year term with the 5-year option term. Thank you. And I'm happy to answer any questions. >> Thank you. Are there any questions or comments from the board? Seeing and hearing none, is there a motion in order? >> So moved.

37
00:12:50.639 --> 00:13:07.519
>> Second. >> All in favor? >> I I >> Any oppose? Eyes have it. Thank you. >> Thank you. Item number five, request authorization to execute a contract renewal for black for blackbod for the NXT, excuse me,

38
00:13:07.519 --> 00:13:23.760
cloud according system for a period of 12 months commencing May 7th, 2026 and ending May 6, 2027 and for a total contract amount not to exceed 64,94010.

39
00:13:23.760 --> 00:13:40.320
Michelle. >> Good afternoon, Vice Chair Shepard, members of the board, Secretary Pis, Direct, uh, Chief Shen. My name is Michelle Goldberg. I'm the director of finance in the city planning department for the BPDA. While much of the AY's operational business is being managed

40
00:13:40.320 --> 00:13:56.320
through city systems, the BPDA still needs to maintain financial systems for its remaining business activity. Currently there are four different business units within financial edge. The BRA, the EDIC, OWD and BLC. I won't

41
00:13:56.320 --> 00:14:12.160
explain the acronyms. Each one of them requires a different accounting standard. We include a curl accounting, inter uh governmental accounting, nonprofit accounting, and grant accounting. Blackbod specializes in the unique needs of these types of entities

42
00:14:12.160 --> 00:14:28.639
and remains the preferred provider. Technology changes rapidly and we reserve the right to review our needs on an annual basis to ensure alignment. Therefore, we seek your authorization to enter into a one-year agreement with Blackbod for financial aid services. Thank you. And I'm happy to answer any

43
00:14:28.639 --> 00:14:43.680
questions you may. >> Thank you. Are there any questions or comments from the board? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. Any oppose? >> Eyes have it. Thank you. >> Thank you. >> Thank you.

44
00:14:43.680 --> 00:14:59.680
Item number six, request authorization to amend a contract with South Coast Improvement Company to complete canopy and platform report, excuse me, repairs at 12 Channel Street in the Raymond L. Flynn Marine Park to extend the

45
00:14:59.680 --> 00:15:18.959
construction completion date to October 30 31st, 2026 and to increase the contract amount not to exceed 726,800 for a total contract amount of 5,496,774 10. Sandra,

46
00:15:18.959 --> 00:15:35.199
>> thank you members of the board. I'm here today to request authorization to amend the construction contract with South Coast Improvement Company for the 12 channel platforming canopy repair project. This is located in the Raymond Elf Flynn Marine Park. This matter was before you last in December of for the

47
00:15:35.199 --> 00:15:52.320
first time in December of 2024 for the initial contract award and again in January February, I'm sorry, January of 2026 for his first amendment. Um, as a reminder, 12 Channel is a nine-story masonry building constructed in 1941 for the US Navy. It features a loading dock

48
00:15:52.320 --> 00:16:08.160
platform and concrete awning that wraps around the building, and it supports critical tenant operations, including shipping, receiving, and building egress. The project addresses the deterioration caused by prolonged exposure to marine and harsh weather conditions, including um spalt concrete

49
00:16:08.160 --> 00:16:25.279
and corroded reinforcing steel. Since our last amendment, we have encountered additional deterioration in the east loading dock, specifically within the existing waffle slab construction. The deterioration has progressed and to maintain the structural integrity, more deck panels must be replaced than we

50
00:16:25.279 --> 00:16:40.320
originally anticipated. To ensure structural integrity of the platform, our project's engineer Gail Associates has recommended that a more robust replacement system um in the project. This includes a design shift and

51
00:16:40.320 --> 00:16:55.120
transitioning from a current waffle slab construction to a thicker um slab design. It also incorporates use of epoxy coated in reinforcing steel and wire mesh. And for long-term um

52
00:16:55.120 --> 00:17:10.640
protection, it's it's including a specialized waterproofing system, and it will be added to minimize the long-term marine climate damage. Additionally, due to earlier unforeseen repairs to the canopy supports, the project schedule

53
00:17:10.640 --> 00:17:28.240
extended to into fall and winter months requiring cold weather protection measures which have increased project costs. We are requesting a 15% increase of $726,800. This figure does include a 15% contingency to cover the approved change

54
00:17:28.240 --> 00:17:45.760
orders. This amendment will bring the final contract amount to 5,496,774. Given the importance of maintaining the functional loading and egress conditions for the tenants, these upgrades represent a necessary investment to ensure the long-term performance,

55
00:17:45.760 --> 00:18:01.120
safety, resilience of the structure. Thank you. And I'm happy to answer any questions. >> Thank you. Are there any questions or comments from the board? Seeing and hearing none, is there a motion on the floor? So moved. >> Second. >> All in favor?

56
00:18:01.120 --> 00:18:16.799
>> Any oppose? Eyes have it. Thank you again. >> Item number seven, personnel. Mike. >> Thank you, uh, vice chair, members of the board, Madame Secretary, and Director Shen. We have a number of items for your consideration on the EDIC

57
00:18:16.799 --> 00:18:33.840
agenda with the exact details included in the board memos. We have one status change in the administration division. Michelle Goldberg, chief procurement officer. We have one contract in the director's office, Brian A. We have seven internships in the communications

58
00:18:33.840 --> 00:18:49.679
division, Matthew Hul. In the real estate division, Lucy Atkinson, Allison Grizzen, and Shane Lunderan. In the urban design division, Vashita Gorla. And in the development review division,

59
00:18:49.679 --> 00:19:07.760
Molly Ping and Jack Denine. Uh also uh in November of 2024, the Salaried Employees of North America, also known as CENA, uh a division of the United Steel Paper and Forestry, Rubber Manufacturing, Energy, Allied

60
00:19:07.760 --> 00:19:23.360
Industrial, and Service Workers International Union, AFL, CIO, CLC, was elected by the majority of an identified unit uh of EDIC employees as their representative for the purpose of collective bargaining.

61
00:19:23.360 --> 00:19:41.120
At uh after a period of negotiations, the union and management reached a tenative agreement that was unanimously approved by the membership. This agreement is a one-year initial contract that covers a period of July 1st, 2025 through June 30th, 2026. This initial

62
00:19:41.120 --> 00:19:57.679
contract outlines the terms and conditions of employment and maintains existing work rules and practices including hours of work, sick time, vacation time, personal and parental leave, holidays and and residency requirements and also health care will

63
00:19:57.679 --> 00:20:14.000
continue to be provided in its current manner. We are asking for a vote to approve the collective bargaining agreement between EDIC and the salaried employees of North America Cena and all related expenses and all related

64
00:20:14.000 --> 00:20:30.799
expenses retroactively effective to July 1st of 2025 and I'll answer any questions you may have. >> Thank you. Just the regular vote or Yes. Okay. Just making sure. All right. Are there any questions or comments from the board?

65
00:20:30.799 --> 00:20:51.360
Seeing and hearing none. Is there a motion on the floor? >> So moved. >> Second. >> Second. All in favor? >> I. >> Any oppose? >> Eyes have it. Thank you. >> Thank you. >> Um asking for a motion to adjourn the EDIC meeting. >> So moved. >> Second.

66
00:20:51.360 --> 00:21:12.240
>> All in favor? I >> I. >> Any oppose? Eyes have it. All right. Thank you for joining the May 14th, 2026 Boston Redevelopment Authority Board meeting. At this time, the Boston Planning

67
00:21:12.240 --> 00:21:28.640
Development Agency is hosting a public meeting in a hybrid setting for the health, safety, and accessibility of Boston residents. Hybrid means that our board meetings are conducted in person at the city hall in our boardroom on the ninth floor and virtually via Zoom

68
00:21:28.640 --> 00:21:44.240
Boston City TV at the time at the same time. Excuse me. For more information and updates, visit bostonplans.org. Open public meeting law requires that I notify the public that this meeting is

69
00:21:44.240 --> 00:21:58.799
being recorded. Please be aware that an audio and a visual recording of this meeting is being made in the broadcast by Boston City TV, which is part of the Boston City of Boston Office of Cable Communication at

70
00:21:58.799 --> 00:22:18.919
Xfinity channel 26 RCN channel 13 and Verizon Files channel 962 and live stream at www.boston.gov/cable. If there is anyone in the audience that is recording this meeting, please identify yourself now.

71
00:22:19.919 --> 00:22:36.159
Thank you. And we will start this meeting with the roll call of officers. Miss Bennett >> present. >> Mr. Oali >> here >> and myself the chair is present. Thank you. Uh today we definitely have a

72
00:22:36.159 --> 00:22:52.240
special guest. Thank you for being live in person. Councelor Durkin, if you have anything to say, please come to the mic. >> Well, usually I address um the board and say, "Dear Chair Roas," but dear Vice Chair Shepard and members of the board. Um and famously, I'm very close with

73
00:22:52.240 --> 00:23:08.240
Director Shen. So, great to see you. Um as District 8 city councelor, I'm I am speaking in support of the West End library redevelopment, which is a huge opportunity for the city and the mayor's office of housing. I want to thank Sheila Dylan, Joe Ber, and their steady

74
00:23:08.240 --> 00:23:24.960
commitment over many years to help carry this project forward. The development has spanned nearly my entire entire tenure on the city council, and I've had the opportunity to see firsthand the level of thought and care that has shaped it. I also want to thank residents Karen Cord Taylor, John Hats, and Suzanne Besser for their early

75
00:23:24.960 --> 00:23:41.600
support of this effort and for seeing the potential of what this site could become for the West End and Beacon Hill communities. Their belief in a project that combines affordable housing, public space, and an updated library to help create momentum and community um has made this project possible. What makes this project so meaningful is it

76
00:23:41.600 --> 00:23:57.520
delivers strong public benefits. And really the benefit here is affordable housing and uh together with the public library um which serves um two neighborhoods I represent and is my public library and where I vote. Um so I'm particularly excited. um residents

77
00:23:57.520 --> 00:24:14.159
have been involved in the whole process. This development has undergone both mayor's office of housing RFP process and article 80 review ensuring the level of review and attention um this important parcel deserves. This project exemplifies community-ledd development where neighborhood priorities and public

78
00:24:14.159 --> 00:24:31.600
benefits remain at the forefront. At the same time, I do want to acknowledge um that uh the uh there are some concerns about loading operations, movein, moveout, and waste collection safety as it pertains to transportation. Um and I just want to

79
00:24:31.600 --> 00:24:47.360
affirm for my constituents that I am in full support of this project. um but that this approval today um does not preclude TAPA review and we're going to have an extensive process around the curbside loading. Um importantly, this

80
00:24:47.360 --> 00:25:02.400
project prioritizes pedestrian and public space on a narrow block of Cambridge Street where sidewalks have been insufficient for the volume of people traveling each day by eliminating eliminating on-site parking, which I famously love. Just kidding. The project

81
00:25:02.400 --> 00:25:19.760
creates an opportunity to dedicate more space to people on foot while supporting a more walkable, sustainable, and accessible urban environment. Beyond the housing and library components, this proposal also delivers additional significant improvements, including expanded green space and upgrades one of

82
00:25:19.760 --> 00:25:36.799
the busiest bike corridors. Together, these improvements can help close long-standing gaps in our built environment and street network that is crucial to the success and vitality of our neighborhoods. I think it's I'd be remiss if I didn't mention POA and Cast Capital and how much work they've put into this project.

83
00:25:36.799 --> 00:25:52.480
Um they have immense experience in the city of Boston which gives me confidence that they're in their ability to complete this project. Um and the West End and Beacon Hill neighborhoods need quality affordable units and I want to recognize their commitment to um to the

84
00:25:52.480 --> 00:26:09.279
environmental sustainability. For these reasons, I urge you to approve the proposal before you today. And thank you for your consideration of my comments. Um, and I also want to speak briefly in support of 419 Boilson Street, um, which is an office to residential conversion. Um, I know that there's no public

85
00:26:09.279 --> 00:26:26.559
testimony for this, um, today, but we do have a lot of support from the community on this conversion. And I just want to acknowledge that, um, there are some concerns about, and as an elected official, I get to state this um, about union construction. So, I urge the developer to use Union Construction. Um,

86
00:26:26.559 --> 00:26:41.360
I want to echo the support of the Neighborhood Association of the Backbay. Um, and I want to thank the leadership of my constituent, John Whiley, who does a great job with the office residential conversion program at the city and it's incredibly important that we um that we

87
00:26:41.360 --> 00:26:58.600
this is really a preservation effort in the city and we're all really thrilled um that this project is happening. So, um, I'm in support of those two projects and hope it's not too long till I see you all again. I love being here. Thank you. >> Thank you, councelor.

88
00:27:05.200 --> 00:27:21.919
>> Item number one. Before I do item number one, I would like to say that uh, President Roas will be in attendance. Sorry for There we go. Right there. Um, >> I didn't become president though. Like I'm chair. >> Chair. I President. Chair. >> I second that motion. Mr. Chair.

89
00:27:21.919 --> 00:27:38.240
>> Yeah. >> I call you my president. There you go. >> I like the sounds of that. >> Item number one, request authorization for the approval of the minutes of the April 16th, 2026 board meeting. >> So moved.

90
00:27:38.240 --> 00:28:02.000
>> Second. >> There's a second. All in favor? >> I. >> I. >> I. >> Any oppose? eyes have it. >> Uh Mr. Vice Chair, I have to uh recuse myself from this next item. Thank you. Item number two, request authorization

91
00:28:02.000 --> 00:28:19.679
to schedule a public hearing for on June 18th, 2026 at 5:30 p.m. or at a date and time to be determined by the director to consider the first amendment to the master plan for plan development area number 128/

92
00:28:19.679 --> 00:28:37.600
street station redevelopment at 776 Summer Street in South Boston and the phase 2 development plan for planned development area number 128L Street Station redevelopment and to consider phase 2 project as a development impact

93
00:28:37.600 --> 00:28:56.159
project. >> Uh with that, we will go straight into the vote. Are there any questions or comments first? >> None. Seeing none, is there a motion on the floor? >> So moved. >> Do we have a second? >> Second. >> There we There's a second. All in favor? >> I >> I.

94
00:28:56.159 --> 00:29:49.240
>> Any oppose? Eyes have it. Thank you. We can get Matt back in here. >> I'll send Matt in. I'm recusing for this next one. >> Yep. Sorry. Let's give Matt a quick second and we'll continue on with item number three.

95
00:29:54.240 --> 00:30:10.480
>> I've returned. >> We need you. No, >> didn't realize it was so close. Sorry. Item number three, request authorization to submit applications to the Commonwealth of Massachusetts Executive Office of Housing and Economic

96
00:30:10.480 --> 00:30:27.520
Development, Mass Works Infrastructure Program, and the Commonwealth of Massachusetts Executive Office of Housing and Livable Communities um housing works infrastructure program in support of various projects in the city of Boston and to enter into a grant

97
00:30:27.520 --> 00:30:43.279
agreement with respective development entities. entities and proponents of said projects for the use of funds from the Mass Works and Housing Works infrastructure programs. Michelle, floor. >> Good afternoon, Vice Chair Shepard,

98
00:30:43.279 --> 00:30:59.360
members of the board, Secretary Bohemis, Director Shen. I'm Michelle Goldberg, director of finance. Before you is a request for authorization for the BPDA to conduct the necessary steps to carry out the application process and administration of funds awarded through

99
00:30:59.360 --> 00:31:15.360
the Mass Works and Houseworks infrastructure program. This program helps cities and public entities get funding to support development projects that will spur economic growth and job creation by enhancing housing, transportation, infrastructure, and community

100
00:31:15.360 --> 00:31:32.159
development. The city of Boston through the BPDA has utilized these programs to facilitate growth and make sites development ready. The memo provides an outline of the various projects under consideration. Given the state's timeline, we seek authorization to

101
00:31:32.159 --> 00:31:48.559
proceed in order to meet the required deadlines. in collaboration with Boston Housing Authority, the mayor's office of economic development, the mayor's office of housing, and the office of intergovernmental relations will participate in the review process to select the projects that will be

102
00:31:48.559 --> 00:32:04.960
submitted. With that, I'm h happy to answer any questions you may have. Thank you. >> Uh, thank you very much. Are there any comments or questions from the board hearing? Seeing none, is there a motion on the floor? >> So moved. >> Second. All in favor?

103
00:32:04.960 --> 00:32:23.840
>> I >> I. >> Any oppose? Eyes have it. Thank you. >> Thank you. >> Our next two items will be read off together, but then have separate votes at the end. So, I will start with item number four. uh request authorization to

104
00:32:23.840 --> 00:32:39.679
enter into a license agreement with TFC 30 Winter LLC for use of the exterior of the property at 30 Winter Street for a June to October 2026

105
00:32:39.679 --> 00:32:56.880
placemaking um activation event as part of the design vision tactical urbanism project. Uh, item number five, request authorization to enter into a license agreement with the BRM LLC to install

106
00:32:56.880 --> 00:33:15.320
temporary public facing and exhibition on street level windows at the China Trade Center located at two Bolston Street supporting a color flows at Liberty Plaza from June 11th to August 1st, 2026.

107
00:33:15.360 --> 00:33:34.559
And with that, Samantha. Nope. >> Help me out, >> please. I apologize. Nothing on the paper. Sorry. >> It's okay. Thank you. And good afternoon. Um, Mr. Vice Chair, members of the board. Um,

108
00:33:34.559 --> 00:33:50.000
my name is Breeze Outlaw. >> Breeze. >> How you doing? Um, back in December 2024, the design vision was adopted to help guide future design strategies informed um to inform how the

109
00:33:50.000 --> 00:34:08.159
built environment is shaped to elevate the quality of urban design. Um, oh, I have some slides. Next slide, please. You can go to the next one. Okay. Um, the design vision reimagine

110
00:34:08.159 --> 00:34:23.280
the design of streets, open spaces, as well as housing. Streets were identified as the first opportunity to explore activation since many communities already activate their the public spaces

111
00:34:23.280 --> 00:34:39.440
in the public realm. Next slide. Um, I'm pleased to share that last year, last fall was our first time doing activation for Color Flows on Winon Street. It was hugely successful with

112
00:34:39.440 --> 00:34:57.440
over um 90% of downtown residents saying that Winter Street felt more welcoming. Um we were able to support local businesses as food vendors to um help with the programming as well as the businesses along Winter Street um reporting higher foot traffic as well as

113
00:34:57.440 --> 00:35:14.480
increase in sales. Next slide. These are just some snapshots of the activation itself. Um, we were able to have colorful seating and planting along the street. Um, we also had lawn games

114
00:35:14.480 --> 00:35:29.359
as well as food trucks and special events. A diversity of different folks were coming out to support the activation um throughout the six weeks that it was active in the fall. Next slide.

115
00:35:29.359 --> 00:35:44.720
This is showing a aerial view of the public art that we installed. Um, this this helped tremendously in regards to um bringing the the street back in regards to this vibrancy. Um, and everyone appreciated that this was an al

116
00:35:44.720 --> 00:36:01.359
added element to it. Next slide. Okay. Um, so we would like to bring Colorflows back to Winter Street, um, and also expand it to a second location, Liberty Tree Plaza in Chinatown. Um, go

117
00:36:01.359 --> 00:36:17.760
to the next slide. Winter Street will bring back. It will run from June 11 to October 31st during the pedestrian hours of 11:00 am to 6 pm. Um it will include again the furnishings, the colorful furnishings

118
00:36:17.760 --> 00:36:33.920
and plants, um food trucks. We will have a light popup flexible programming at 30 Winter. The license agreement will allow us to do that. And most of that is about uh making sure we deter unwelcoming behavior that usually happens in that

119
00:36:33.920 --> 00:36:50.560
space. Next slide. We will also, this is a site plan illustrating um the mural installation that we'll do. So we'll be adding public art to this as well um to continue bringing that welcoming and vibrant um

120
00:36:50.560 --> 00:37:06.800
energy to the space. Um and that concludes that piece of Winter Street. And the next slide I could introduce color flows at Winter Street at Liberty Tree Plaza. Um, this will be a different vibe, different energy in regards to

121
00:37:06.800 --> 00:37:22.560
color flows. Um, mostly being informed by the context of Chinatown and the way it's used. Um, this will run from June 11th to August 1st from 10 a.m. to 5:00 pm and again be an added um enhancement

122
00:37:22.560 --> 00:37:38.240
to the public realm being a public space that people can come to as they traverse from um different neighborhoods. Um this will also be a site that is curated by a theme of with care and it will be a site that will be reinterpreting the site

123
00:37:38.240 --> 00:37:54.640
legacy um as a civic gathering space historically and then um layering on contemporary artistic expression and cultural programming. That cultural programming will include um as you can see from this um rendering, lion dance, musical

124
00:37:54.640 --> 00:38:09.440
performances. Um and then we'll also have food vending um from a ship in a shipping container by local Chinatown businesses. Um and then we'll be installing three different public art installations that I'll go into further

125
00:38:09.440 --> 00:38:25.599
on the next slide. Um this first one is the storefront window mural. Um it will this is what the license agreement will allow for this temporary installation of this. Um the imagery is depicting

126
00:38:25.599 --> 00:38:42.000
the the cycle transition. Um and so they're putting a traditional Chinese scroll print and superimposing everyday Chinat town experiences um and leveraging that as a way to um demonstrate care. Next slide.

127
00:38:42.000 --> 00:38:58.880
The second one is a over overhead fabric installation. Um and this is really about taking the traditional medicinal um white flower oil um which is used as for healing and so the banners will be

128
00:38:58.880 --> 00:39:13.599
representing healing and protection over the site during the activation. And the next slide and we'll be wrapping the shipping container that we'll be using for the food vendors. Um, and this is inspired by the Chinatown worker statue. And so

129
00:39:13.599 --> 00:39:31.599
the artist has ink printed and digitized um, objects that are used by garment workers, um, grandmothers, restaurant workers, and using those as a symbol of um, small gestures and their labor as it

130
00:39:31.599 --> 00:39:47.920
supports the community. Um and so you know you have frog buttons um um mesh b b b b b b b b b b b b b b b b b b b b baskets in a lot of different items um that will be reflecting on that. Um so just want to give you a sense of what to expect and what you'll

131
00:39:47.920 --> 00:40:04.640
see. Hope to see you there. That concludes my presentation. Thank you, Bree. Thank you for that presentation. I will reread each number and we'll vote on them separately. So item number four, request authorization to enter to a license agreement with TFC 30 Winter LLC

132
00:40:04.640 --> 00:40:21.839
for use of exterior of the property at 30 Winter Street for a June to October 2026 placemaking activation event as part of the design vision tactical urbanism project. Are there any questions or comments from the board?

133
00:40:21.839 --> 00:40:36.480
Seeing and hearing none, is there a motion on the floor? >> So move. >> Second. >> Second. All in favor? >> I >> I. >> Any oppose? >> Eyes have it. Um, item number five, request authorization to enter to a license agreement with BRM LLC to

134
00:40:36.480 --> 00:40:53.040
install a temporary public facing art exhibit exhibition, excuse me, on street level windows at the Chinatown Trade Center located at two Bolston Street supporting color flows at Liberty Plaza from June 11th to August 1st, 2026.

135
00:40:53.040 --> 00:41:09.760
Are there any questions or comments from the board? I >> I do have a comment uh or qu both a comment and a question Mr. Chair and I I saved it for this one. Uh so Breeze, thank you. The importance of public art of activation of space is so critical especially in a post2020 world where we

136
00:41:09.760 --> 00:41:25.839
don't see as much activity downtown. So I love this. I love seeing it. I've worked in and around downtown crossing for 20 plus years my entire professional career and it's it's always exciting to see. My question is this. Why are we limiting the Chinatown activation um for essentially 6 weeks and ending it on

137
00:41:25.839 --> 00:41:41.839
August 1st? >> That's a great question. Um most of that is due to constraints um in regards to the budget, but also with this being the first time that we're activating the space. We're piling pilot like testing it out. >> Um last year for Winter Street, it was a

138
00:41:41.839 --> 00:41:58.079
short-term activation. We had huge success from that and so we're returning for a longer period. I imagine we can do the same for this one. um given the investment that we're putting in and the partners that we have. >> Fair enough. That makes sense. Um I look forward to seeing it and I look forward to seeing it even longer next summer. So

139
00:41:58.079 --> 00:42:13.200
>> awesome. >> Thank you. >> Thank you. >> Agree. This is fantastic. Thank you, Breeze. Thank you so much. >> Uh if there are no further questions or comments, is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. Thank you, Bree.

140
00:42:13.200 --> 00:42:32.240
>> Thank you. Item number six, requests authorization to enter into a license agreement with the Warf District Council for the use of a portion of Long Warf between the customhouse block and

141
00:42:32.240 --> 00:42:49.440
the and the BPDA pavilion to place anformational kiosk. bring awareness for the forecasted vulnerability of the Boston's Wararf district to sea level rise for a period of six months commencing June 1st, 2026 and ending

142
00:42:49.440 --> 00:43:06.000
November 30th, 2026 with two six-month term renewal options. Samantha, >> good afternoon, Vice Chair, members of the board, Madame Secretary, and Director Shen. I'm here to request approval to enter a license with the Warf District Council for approximately 20 square ft at the end of Longworf

143
00:43:06.000 --> 00:43:22.480
between the custom house block and the BPD pavilion. Established in 2010, the Warf District Council is a 501c3 nonprofit neighborhood organization made up of large and small businesses, residential condominium associations, nonprofit institutions, and individuals

144
00:43:22.480 --> 00:43:38.800
who work and live in the Warf District. The Wararf District Council works to better the Wararf District and its future by bringing community members, businesses, and nonprofits together to discuss matters impacting the community. The Warf District Council is proposing to place anformational kiosk at the end

145
00:43:38.800 --> 00:43:55.359
of Longworf. The proposed informationational kiosk is intended to bring awareness to the of the forecasted vulnerability of Boston's Wararf district to sea to sea level rise and initiatives underway to plan and construct a resilient waterfront. The kiosk will also include a QR code that

146
00:43:55.359 --> 00:44:11.119
patrons can scan to learn more and stay informed. The target audience for the kiosk is Boston residents, workers, and tourists. Staff recommend entering into a license agreement with the Warf District Council for a six-month license term which will commence on June 1, 2026 and end on

147
00:44:11.119 --> 00:44:28.720
November 30th, 2026, whereupon at the discretion of the director, the license can be renewed for up to two additional six-month terms after November 30th, 2026. There will be no fee for the use of the license area due to the comm community benefit nature of the per property use.

148
00:44:28.720 --> 00:44:45.119
BPDA staff recommends that director be authorized to enter into a license agreement with the Warf District Council for the use and occupancy of a portion of approx approximately 20 square feet to place anformational kiosk at the end of Longwarf between the custom house block and BPD pavilion. Thank you and I'm happy to answer any questions.

149
00:44:45.119 --> 00:45:01.359
>> Thank you. Are there any questions or comments from the board? >> Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> There's a second. All in favor? >> I. Any oppose? >> Eyes have it. Thank you. >> Thank you. Item number seven, request authorization to amend the license

150
00:45:01.359 --> 00:45:18.240
agreement with CAP Longwarf LLC for the use of approximately 15,000 square ft of land adjacent to the Chart House restaurant on Long Warf for a monthly customer and visitor parking for a period of one year commencing June 1st,

151
00:45:18.240 --> 00:45:34.160
2026 and ending May 31st, 2027. Samantha. >> Good afternoon, Vice Chair, members of the board, Madam Secretary, and Director Shen. I'm here to request authorization to amend the existing license agreement between the Boston Redevelopment Authority and Cap Longworf LLC, a

152
00:45:34.160 --> 00:45:50.240
capital's property affiliate to extend the term expiration date to May 30th, 2027, and to establish a new license fee for the use of approximately 15,000 ft of land adjacent to the Chart House restaurant on Longworf for monthly and visitor parking. In 2015, CAP Longworf

153
00:45:50.240 --> 00:46:05.599
LLC purchased the Longworth LLC properties and BPDA consented to the assignment of the above of the above reference license to Cap Longwarf. Capitals Capital Properties is privately founded in Boston, Massachusetts in 1977. Capital Properties has developed,

154
00:46:05.599 --> 00:46:22.160
acquired, and managed over 18,000 apartment units and 8 million square ft of office space in major markets primarily between Boston and Atlanta. BPD staff has analyzed the current market for surface parking and has determined that it's that it is in BPDA's financial and regulatory interest

155
00:46:22.160 --> 00:46:36.880
to extend the license the existing license with CAP Longworf LLC rather than BPDA take on the responsibilities and expenses of operating the lot itself or with outside contractors. Staff is therefore recommending that the license term expiration date be extended

156
00:46:36.880 --> 00:46:56.720
extended to May 31st, 2027 on the same terms and conditions as the current license and the only exception being that the monthly fee payable to the BPDA will increase to 16,642 $16,462,000 per month and $199,710,000

157
00:46:56.720 --> 00:47:11.680
per year. The new license fee is consistent with the market and is a 5% increase from the previous year license rate. BPDA is only is currently only contemplating a one-year agreement with Caplong Warf as the site is anticipated to be converted to a new open space and

158
00:47:11.680 --> 00:47:27.040
a gateway to Boston Harbor Islands. BPDA staff recommends the director be authorized to amend the license the existing license with CAP Longworf to extend the expiration date of the existing license agreement to May 31st, 2027. Thank you. Thank you. I'm happy to answer any questions.

159
00:47:27.040 --> 00:47:42.640
>> Thank you. Are there any questions or comments from the board? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. >> Thank you. >> Thank you. Item number eight, request authorization

160
00:47:42.640 --> 00:47:57.680
to assign the lease held by Clifford Long Trustee and Second Massav Realy Trust for building 120 within the historic monument area of the Charlestown Navalyard Navyyard to the US

161
00:47:57.680 --> 00:48:13.920
Constitution Museum, Inc. Liz. >> Uh, thank you, Vice Chair. Uh, good afternoon, members of the board. I am here today request an authorization for the reassignment of the building 120 lease from Clifford Long Trustee of Second Massav Royalty Trust to the USS

162
00:48:13.920 --> 00:48:31.119
Constitution Museum Inc. building 120 is located adjacent to 6th Street within the historic monu monument area of Charlestown Navyyard and consists of an approximately 14,875 square foot three-story office building.

163
00:48:31.119 --> 00:48:47.440
By way of background, the leaseold interest was originally acquired through the public auction in 1996 by Navy Yard dispensary dispensary LLC and later assigned in 2005 to Clifford Young, trustee of second mass royalty trust.

164
00:48:47.440 --> 00:49:03.359
The current tenant has requested BPDA consent to extend um the requirements under the lease and to assign its remaining leaseold interest to the USS Constitution Museum uh Inc. The USS Constitution Museum is a nationally

165
00:49:03.359 --> 00:49:19.359
recognized nonprofit cultural and educational institution located within the Charlestown Navyyard. Established in 1972, the museum serves hundreds of thousands of visitors annually through interactive exhibits, educational programming, and public events focused

166
00:49:19.359 --> 00:49:34.960
on the history of the USS Constitution and the United States Navy. The museum plays an important role in activating and preserving the historic monument area while complementing the efforts of the National Park Service and supporting tourism and public engagement

167
00:49:34.960 --> 00:49:51.680
along the Charleston waterfront. Under the proposed assignment, the leaseold interest would be transferred for no monetary consideration and no substantive changes to the existing lease um is being requested. The USS Constitution Museum would continue to

168
00:49:51.680 --> 00:50:08.000
remain responsible for all obligations under the lease, including the payment of annual base rent of 14,400. Staff believes the proposed assignment supports the continued stewardship and activation of this important historic asset and is consistent with BPDA's

169
00:50:08.000 --> 00:50:23.200
long-term goals for the Charleston Navy Yard. Accordingly, staff recommends the approval of the requested authorization for the director to consent to the assignment and execute our related agreements and documents. Thank you. And I'm here to answer any questions.

170
00:50:23.200 --> 00:50:38.160
>> Thank you. Are there any questions or comments from the board? Seeing and hearing none, what's a motion on the floor? >> So moved. >> Second. >> All in favor? I. >> Any oppose? >> Eyes have it. Thank you. >> Thank you.

171
00:50:38.160 --> 00:50:55.119
Our next two items, item number nine and number 10. Uh these two items will be will be presented jointly uh with separate board votes to follow. So I'll read through both of them and then we'll go through the presentation and we'll do

172
00:50:55.119 --> 00:51:10.480
what we have to do up here to vote. Uh item number nine request authorization to extend the tenative designation of Garrison Troder Neighborhood Association, Inc. for the sale in the redevelopment of partial S- 12B in

173
00:51:10.480 --> 00:51:27.040
Washington Park urban renewal area project number Mass R-24 known as 16 through 20 Towns and Street in Roxbury for one year until May 31st, 2027. Item number 10, request authorization to

174
00:51:27.040 --> 00:51:44.319
extend the tenative designation of Garrison Troy Neighborhood Association, Inc. for the sale and redevelopment of parcel S-12C in the Washington Park urban renewal area. Project number mass R-24 known as 48 Towns and Street in Roxbury

175
00:51:44.319 --> 00:52:01.440
for one one year for for one one year until May 31st, 2027. >> Ben, >> uh thank you, Vice Chair Shepard and members of the board. um 16 to 20 Towns and Street and 48 Townsen Street consist of approximately 12,000 and 17,000

176
00:52:01.440 --> 00:52:18.800
square feet of vacant land respectively. The board granted Garrison Troder Neighborhood Association tenative designation um as the developer of both properties on May 16, 2024 and extended this designation last May. The developer proposes an urban wild for 16 to 20

177
00:52:18.800 --> 00:52:34.000
Townson Street and a community garden on 48 Townson Street for community and educational uses, providing for both both food and security and access to nature and open space. The proposed designs for the community garden include uh raised plant beds for growing produce

178
00:52:34.000 --> 00:52:49.680
and herbs. Since the 2024 tenative designation award, the project team has received phase one environmental reports for the property, further development, conceptual plans for the proposal, and applied for funding. Most recently, the project received partial project funding

179
00:52:49.680 --> 00:53:06.319
for 48 for the 48 Townsen Street Community Garden in the form of CPA funds and is waiting to hear on a funding request to the mayor's office of housing for the remaining amount. If awarded by Mo, this would allow them to start construction potentially later this year. In this light is my hope to

180
00:53:06.319 --> 00:53:21.920
come before you within the next few months, maybe the next month to request final designation for 48 towns and for 16 to 20 Townson Street. The developer is sinking through the myriad of funding sources to help fund the project. We are which we are confident they will be able

181
00:53:21.920 --> 00:53:38.800
to do during the requested uh and proposed tenant designation period of one year for both projects. The developer plans to seek and secure funding as well as round out any remaining design items and permits needed to construct the project. Uh thank you. I'm happy to answer any questions.

182
00:53:38.800 --> 00:53:54.880
>> Thank you, Ben. All right. To uh have the vote, I will read number nine and number 10 again. Uh item number nine requests authorization to extend the tenative designation of Gastron Neighborhood Association Inc. for the sale and redevelopment of

183
00:53:54.880 --> 00:54:12.480
partial S-12B in the Washington Park urban renewal area project number Mass R-24 known as 16 through 20 Townren Street in the Roxbury for one year until May 31st, 2027. Are there any questions or comments from

184
00:54:12.480 --> 00:54:28.720
the board? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. Item number 10, request authorization to extend the tenative designation of the Garrison Trotter Neighborhood Association, Inc.

185
00:54:28.720 --> 00:54:46.400
for the sale and redevelopment of a parcel S-12C in the Washington Park Urban Renewal Area, project number Mass R-24, known as 48 Towns and Street in Roxbury for 1 year until May 31st, 2027.

186
00:54:46.400 --> 00:55:06.000
Are there any questions or comments from the board? hearing and seeing none. Is there a motion on the floor? >> So moved. >> Second. >> There's a second. All in favor? >> I. >> Any oppose? Eyes have it. Thank you. >> Thank you. >> Uh, another announcement. Um, the next

187
00:55:06.000 --> 00:55:22.000
four items will be presented jointly with separate board votes similar to what we just did. Uh, I will read off all four of them. Item number 11, request authorization to award tenative designation status to AEUN for the sale

188
00:55:22.000 --> 00:55:40.400
and redevelopment of 11 through13 Katawa Street. Yes. Located in the Washington Park urban renewal area, project number Mass R-24 in the Roxbury neighborhood as part of the Welcome Home Boston phase 3 request for proposal

189
00:55:40.400 --> 00:55:58.240
proposal. Um item number 12 request authorization to award tenative designation status to a joint venture between K&G Realy Corp. Genuine Construction and Consulting LLC in Rise Builders Inc. for the sale and

190
00:55:58.240 --> 00:56:16.079
redevelopment of 14 Kawa Street located in Washington Park urban renewal area. Project number mass R-24 in the Roxbury neighborhood as part of the welcome home Boston phase 3 request for proposal. Item number 13 requests authorization to

191
00:56:16.079 --> 00:56:31.280
award tenative designation status to a joint venture between historic build stack architectural and MCMI for the sale and redevelopment of 19 Laurel Street located in Washington Park

192
00:56:31.280 --> 00:56:49.040
urbal renewal area. Project number mass R-24 in the Roxbury neighborhood as part of a welcome home Boston phase 3 request for proposal. Item number 14 request authorization to award tenative designated status to Ambry Development

193
00:56:49.040 --> 00:57:05.119
for the sale and redevelopment of 100 Roofing Street located in the Washington Park urban renewal area. project number mass R-24 in the Roxbury neighborhood as part of a welcome home Boston phase 3 request for for proposal.

194
00:57:05.119 --> 00:57:20.480
I just want to make sure. Okay, that is good. You the floor is yours. >> Thank you so much vice president and afternoon members of the board. I am here to recommend tenative destination status of four development teams for the sale and redevelopment of four parcels

195
00:57:20.480 --> 00:57:36.160
in Roxberry as part of the welcome home Boston phase 3 RFP. I have a brief slide deck uh to summarize the RFP in each of the proposals. So um in 2022 the mayor's office of housing uh launched the welcome home Boston initiative with the

196
00:57:36.160 --> 00:57:51.680
goal to create new family familysiz condo units on vacant city-owned land. This actually tested a new cluster approach of offering a group of parcels in geographic proximity to a single scattered site request for proposal or

197
00:57:51.680 --> 00:58:09.200
RFP uh which established a more effective disposition process for small infill parcels that um have been proven more difficult to move. Building on the first two phases which yielded a total of 144 affordable home ownership units at 80 and 100% IMI for air and medium

198
00:58:09.200 --> 00:58:25.359
income, the BPDA joined forces to lead uh phase three to combine the resources, expertise and land portfolio of each department for a comprehensive disposition effort. Next slide, please. Um so phase three specifically targets

199
00:58:25.359 --> 00:58:42.319
households earning between 120 to 135% of the area median income uh who are identified as this missing middle demographic that are currently underserved by existing affordable housing programs. These families earn too much to qualify for traditional

200
00:58:42.319 --> 00:58:57.040
incomerestricted programs but too little to compete in Boston's increasingly expensive housing market. This need was echoed through the numerous public comments that we received during the community meetings and our surveys. Next slide, please.

201
00:58:57.040 --> 00:59:12.559
Um, so as far back as November 2024, MOA uh Mo and BPDA staff uh worked in close coordination with Boston's development community to identify the building blocks of a program that could support housing for this missing middle. Um on

202
00:59:12.559 --> 00:59:29.839
the next slide um summarizes our community engagement which began in early 2025. Um so um the community engagement for this project uh spanned uh it was extensive and kind of spanned all uh medium and formats including six

203
00:59:29.839 --> 00:59:45.280
public meetings uh and tailored outreach to abutters neighborhood associations and elected officials as well as the first home survey that received over 140 responses across all neighborhoods of Boston. The community process echoed a

204
00:59:45.280 --> 01:00:02.240
strong need u for home ownership options for families in this demographic and identified key preferences and trade-offs of both the firsttime homeowners as well as the list of priorities that the neighborhoods had uh that could help guide the proposals. Next slide please.

205
01:00:02.240 --> 01:00:18.880
Uh so combining our own research and feedback from uh both the development industry and the neighborhood communities uh BPDA and MO staff uh formulated this framework for phase three. Um so you know um starting with the city-led preliminary due diligence

206
01:00:18.880 --> 01:00:35.599
which reduces risk. Um leveraging public land reduces acquisition cost and encouraging innovation in housing delivery reduces soft and hard costs. Uh these savings are designed to deliver more affordable units to first-time home buyers without the need of additional

207
01:00:35.599 --> 01:00:51.920
public subsidy. Next slide, please. So on July 17th, 2025, WPDA board authorized the welcome home phase 3 RFP. The final RFP, which was released on June 30th, 2025, included 11 parcels

208
01:00:51.920 --> 01:01:10.400
comprised of seven owned by the city of Boston under the care and custody of the mayor's office of housing and four parcels owned by the BPDA uh organized as nine distinct sites. So, these properties range in size from approximately 3,000 to 6500 uh 6,500 ft²

209
01:01:10.400 --> 01:01:26.000
and have an appraised value of approximately $300,000 each. Uh these parcels were offered at a nominal fee of $100 each. Next slide, please. Um so the development objectives of the RFP focus on the creation of quality home

210
01:01:26.000 --> 01:01:44.000
ownership units at the lowest possible sales price and the community priorities that were identified through the public process. And the comparative evaluation criteria on the right uh sets out five areas in which the proposals would be assessed. Um on the next slide. Um so at

211
01:01:44.000 --> 01:02:00.000
our proposal deadline on October 15th, 2025, WPDA received 11 proposals. Um and we held two community meetings where the developers presented their proposals directly to the community and the internal evaluation committee uh which

212
01:02:00.000 --> 01:02:17.839
consisted of 13 staff from both BPD and MO evaluated the proposals to select the best um uh selection for each site in accordance to the criteria that was um set forth and the public feedback received. Um the next slide summarizes

213
01:02:17.839 --> 01:02:33.920
uh the seven teams that the committee is recommending for all nine sites offered in the RFP uh which are expected to create 41 anticipated units. If you could advance one more. So as you may recall uh the sites are under two

214
01:02:33.920 --> 01:02:51.200
different ownership. So accordingly, the five sites owned by the MO uh in sort of this yellowish color uh were designated by the PFC in the um April 29th meeting. So the four votes before you tonight are for the Roxberry sites owned by the BPDA

215
01:02:51.200 --> 01:03:06.400
highlighted in blue. Next slide, please. Um so here is a map of the four sites in Roxberry for today's vote. Uh so they're all kind of situated along Humbled A. There's a cluster of three sites at Kataba Street

216
01:03:06.400 --> 01:03:23.520
um and one further away at 100 Ruthan. Uh these are all kind of in predominantly well settled residential areas. Um just these um random vacant lots kind of in between um these duplex and uh triplex kind of fabric. Uh next

217
01:03:23.520 --> 01:03:38.799
slide. So uh the first um site on the vote is 19 Laurel which is a 3,300 square ft site. Uh for here we're recommending HBSAMCM uh which is a joint venture between

218
01:03:38.799 --> 01:03:55.440
historic build the developer stack architecture architect and MCM builders the general contractor. They are proposing three units and three parking spaces and um the committee thought this proposal um did a really commendable job uh mediating the difficult site. This is

219
01:03:55.440 --> 01:04:11.280
a really narrow uh site with difficult dimensions and um they did really well with the constraints here. On the next slide uh on 11 to13 KFABA uh this is a 5,570 square feet uh vacant parcel where we're

220
01:04:11.280 --> 01:04:26.960
recommending Acidone which is a CDC and also at the developer from welcome home phase one. Uh they're proposing six units and three parking spaces. And um something to highlight on this proposal was really strong community support um

221
01:04:26.960 --> 01:04:42.240
as well as the design that was very responsive to the public feedback. Um on the next slide we have 14 Kataba which is right across the street. This is a 4,950 square ft parcel of land where where

222
01:04:42.240 --> 01:04:59.520
where we are recommending 14 Kataba Jav which is a joint venture between K&G realy rice builder genuine construction um and who are actually developers from welcome home phase 2 and they are um proposing three units and three parking

223
01:04:59.520 --> 01:05:16.400
spaces um and again you know we selected this proposal based on their design which was very responsive to public feed feedback. Um, and I'd also like to note that they will be trying out this panelized construction as part of this um, uh, innovation in housing delivery

224
01:05:16.400 --> 01:05:33.440
mode. Next slide, please. So, our last last site of the vote tonight here is 100 Ruthfren, which is a 5,394 square foot of land. We are recommending Embry Development um who is also a

225
01:05:33.440 --> 01:05:47.920
welcome home phase three developer uh who is and they are proposing six units and three parking spaces and in in addition to the design that was very responsive to public feedback. Um we are very impressed with the strong DEI plan

226
01:05:47.920 --> 01:06:05.200
of this proposal as well. Uh so on the next slide um I'll put up the summary of the proposals that we're recommending. Again, uh we're really proud to say we're advancing with 100% of all the sites we went out uh on the RFP. This is a significant improvement from the

227
01:06:05.200 --> 01:06:22.160
previous phases um which typically yielded about a little more than half. Um I think this is um largely attributable to the rigorous level of due diligence um that we did. It was painful but it definitely paid off. Um and you know we are having two projects

228
01:06:22.160 --> 01:06:38.880
that are testing this off-site innovation strategy as well as three teams that are testing a joint venture model to create more efficiency uh between the project teams and uh we're also happy to see many alums of the previous phases um you know which is

229
01:06:38.880 --> 01:06:54.400
very well in alignment with previous welcome homes um goals to support uh emerging and minority developers. Um so at this time I am recommending tenative designation of a period of 12 months for these four development teams. Um during

230
01:06:54.400 --> 01:07:10.160
which time they will be advancing their entitlement and assembling their uh financing before we can return to the board for final destination and conveyance of the property. Thank you. I'm happy to answer any questions. >> Thank you. Um I will read each item 11

231
01:07:10.160 --> 01:07:27.039
through 14 off individually so we can have separate votes for each parcel. So, I'll start with uh item number 11. Request authorization to award tenative designation status to a I'm going to call it ace done. >> Yeah. >> Okay. Ace done. Yep. For the sale and

232
01:07:27.039 --> 01:07:45.359
redevelopment of 11 through 13 Katawa Street located in the Washington Park urban renewal area. project number mass R-24 in the Roxberry neighborhood as part of the Welcome Home Boston phase 3 request for proposal.

233
01:07:45.359 --> 01:08:00.240
Do the board members do we have any questions or comments? I'll throw in my comments for this one for all of them, which is uh uh I know director Chen is always champing at the bit to figure out what my favorite project will be and it's it's odd to give just tentative designation, but I'm

234
01:08:00.240 --> 01:08:16.000
going to award it for all these projects because the welcome home Boston pro program is so important. This has been something we as a city have been grappling with for 400 years. And um I particularly love the design of Laurel and Ruth Finn. Those are nice looking buildings. So, like I I urge everyone

235
01:08:16.000 --> 01:08:32.480
watching like like let's get more interesting uh uh uh architectural with with these projects. These look great. I'm so excited. Um and I guess this is a question you so the these are the the BPDA property. So we have oversight the the other ones in park and Dorchester

236
01:08:32.480 --> 01:08:48.560
that's Mo and they've already advanced that they they've given their their equivalent of tens of designation status. >> Exactly. Mhm. >> So they'll be all these projects will be happening concurrently and hopefully groundbreaking in the same general timeline. >> That's what we're going to try to do. >> Great. Okay. Thank you.

237
01:08:48.560 --> 01:09:04.000
>> Yep. >> Uh there any other questions or comments for the board? >> Congratulations. This is great getting to this uh 100% >> award. >> Thank you. Uh is there a motion on the floor? >> So moved.

238
01:09:04.000 --> 01:09:18.480
>> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. Thank you. Item number 12, request authorization to award tenative designation status to a joint venture between K&G. Yep. K&G

239
01:09:18.480 --> 01:09:32.960
Royalty Corp. >> We on 12. >> Oh, well, I have to read them. >> Oh, I'm sorry. I'm sorry. >> Nope. All good. >> Silly me. >> Venture between K&G Realy Group, Genuine Construction, and Consultant LLC and E-

240
01:09:32.960 --> 01:09:50.719
Rise Builders, Inc. for the sale and redevelopment of 14 Katawa Street located in Washington Park Urban Renewal Area Num project number Mass R-24 in the Roxbury neighborhood as part of the welcome home Boston phase three request

241
01:09:50.719 --> 01:10:05.760
for proposal. Uh are there any questions or comments from the board? Seeing and hearing none, is there a motion on the floor? >> So move. >> Second. >> Second. All in favor? >> I. >> Any oppose? Eyes have it. Item number

242
01:10:05.760 --> 01:10:22.080
13, request authorization to award tentative designation status to a joint venture between Historic Built Stack Architecture and MCMI for the sale and redevelopment of 19 Laurel Street located in the Washington Park urban renewal area

243
01:10:22.080 --> 01:10:39.280
project number Mass R-24 in the Roxbury neighborhood as part of the Welcome Home Boston phase 3 request for proposal. Are there any questions or comments from the board? Seeing and hearing none, is there a motion on the floor? >> So move. >> Second. >> There's a second. All in favor?

244
01:10:39.280 --> 01:10:54.400
>> I. >> Any oppose? Eyes have it. Item number 14, request authorization to award tenative designation status to Ambry Development for the sale and redevelopment of 100 roof roof street

245
01:10:54.400 --> 01:11:10.480
located in the Washington Park urban renewal area. Project number mass R-24 in the Roxbury neighborhood as part of the Welcome Home Boston phase three request for proposal. Are there any questions accomplished from the board? >> Seeing and hearing none. Is there a

246
01:11:10.480 --> 01:11:32.239
motion on the floor? >> So moved. >> Second. >> There's a second. All in favor? >> I. >> Any opposed? Eyes have it. Thank you. >> Thank you so much. Item number 15, request authorization to adopt an order of taking for the taking

247
01:11:32.239 --> 01:11:48.640
parcel located at 212 Stewart Street in the South Cove urban renewal area project number mass R-92 and authorization authorize the director to enter into the

248
01:11:48.640 --> 01:12:07.760
executed deed for the GU U GV I 1212 oh excuse me 212 Stewart Property Owning LLC and uh indemnification excuse me agreement and any and all

249
01:12:07.760 --> 01:12:23.440
other related instruments agreements and documents in the connection with the tagen parcel for the project. John. >> Uh, thank you, Vice Chair and members of the board, Secretary Paul Hamus and Director Chen. My name is John Splain.

250
01:12:23.440 --> 01:12:39.920
I'm an attorney in the office of general counsel. Before you today is a request for authorization to adopt an order of taking for taking parcel in connection with a project located at 212 Stewart Street and authorize the director to enter into and execute a deed to GUGV2

251
01:12:39.920 --> 01:12:55.440
Stewart Property Owning LLC an indemnification agreement and any and all related instruments agreements and documents in connection with the taking parcel which the director and his sole discretion deems appropriate necessary and upon terms and conditions determined to be in the best interest of the BPD.

252
01:12:55.440 --> 01:13:11.600
PDA. For background, this project was approved by the PPDA board on June 15th, 2017 and completed construction on August 11th, 2022. The developer is uh since the completion of construction has determined that approximately 43 square

253
01:13:11.600 --> 01:13:26.800
ft of the building uh encroaches on the air rights of the city. In order to provide a clean title for the project and alleviate this encroachment, this order of taking and transfer is being sought. This taking was previously approved on September 18th, 2025 and the

254
01:13:26.800 --> 01:13:44.400
BPDA board um approved um this taking at that meeting and it is since expired and thus this subsequent board action is being sought. This transfer shall be done for the monetary consideration of $15,000 an amount determined by an appraisal com uh completed by Hunan

255
01:13:44.400 --> 01:13:59.520
Appraisal Services. Based on the foregoing, staff recommends that the board adopt an order of taking for the taking parcel in connection with the project at 212 Stewart Street and authorize the director to enter into and execute a deed um with this 212 Stewart

256
01:13:59.520 --> 01:14:15.760
Street property owner an indemnification agreement in any and all other related instruments and agreements and documents in connection with this taking parcel for the project. U thank you and I'm happy to answer any questions. >> Uh thank you. Are there any questions or comments from the board?

257
01:14:15.760 --> 01:14:32.719
Seeing here, none. Is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. Thank you. >> Awesome. Thank you everyone. >> The next two items will be presented jointly with separate board votes to

258
01:14:32.719 --> 01:14:48.719
follow. So I will read both items. Item number 16 and item number 17. uh request authorization to adopt an amendment to the plan downtown that includes new Chinatown historic context design guidelines which will guide the BPDA and

259
01:14:48.719 --> 01:15:06.159
the community on the design development and review of the projects that enhance Chinatown's unique and historic fabric. Item number 17 requests authorization to adopt one text amendment for article 43,

260
01:15:06.159 --> 01:15:23.679
article 8 to establish new Chinatown neighborhood district zoning regulations and to text amendments for the new article 34 and article 8 to establish a new set of institutional zoning districts and

261
01:15:23.679 --> 01:15:40.480
number three additional minor text amendments in the article two artic Article 3 and article 23, article 31, article 49A and article 89 to ensure consistency throughout the code and for

262
01:15:40.480 --> 01:15:57.600
map amendments to zoning map 1 CGN. With that, Jack, floor is yours. >> Thank you. Uh, good afternoon, Vice Chair Shepard, members of the board, Chief Shen, and Secretary Palis. My name is Jack Halverson. I'm a planner on the zoning reform team here and I'm really

263
01:15:57.600 --> 01:16:13.520
excited to share with you today new proposed zoning for Chinatown and a new set of Chinatown design guidelines. Next slide. This initiative started with Plan Downtown where it became clear that Chinatown would need its own resoning process. Chinatown serves as a historic

264
01:16:13.520 --> 01:16:28.960
gateway for immigrants and their families and a hub for housing, jobs, diverse businesses, and cultural activity. The neighborhood has faced challenges like urban renewal, highway construction, and development pressure, but continues to be a vibrant center for a diverse range of residents, workers,

265
01:16:28.960 --> 01:16:46.800
and visitors. Next slide. The first key phase of this process was planned downtown itself, which was adopted in 2023. In 2024, from April, February to April, we held a series of public meetings and workshops focused on specific zoning goals for Chinatown.

266
01:16:46.800 --> 01:17:02.159
Then in fall of 2024, the planning department released the first Chinatown zoning draft and design guidelines. From then until February of last year, we held many public meetings and office hours, both in person and virtual, um, and some of which were targeted specifically towards property owners and

267
01:17:02.159 --> 01:17:18.400
business owners. We engaged directly with over 350 people and collected over 700 written points of feedback on the first draft of this proposed zoning and the design guidelines. Since the spring of 2025, we've been refining the draft zoning and design guidelines based on

268
01:17:18.400 --> 01:17:35.199
feedback we heard on those first drafts. And just last month, we released an updated draft of both items and held a final closeout public meeting. Next slide. So now I'll provide a quick overview of each of the new proposed zoning districts before getting uh into more

269
01:17:35.199 --> 01:17:51.840
detail on each of them. The residential one or R1 subdist is focused on maintaining what's happening today in the older rowhouse areas of the neighborhood. The community commercial or CC subdist includes the commercial heart of Chinatown and is aimed at preserving the

270
01:17:51.840 --> 01:18:09.040
existing small businesses and affordable housing, but also making it easier to open new businesses and update and renovate buildings. The residential 10 or R10 subdist intended for the larger apartment building parts of Chinatown and seeks to continue that character. The Skylow CT

271
01:18:09.040 --> 01:18:25.360
subdist is a new application of the recently adopted skyline zoning and is centered along Essex Street where Chinatown meets the rest of downtown to the north. The institutional 2 or IS-2 district is a new institutional district mapped where the TUS medical and TUS University

272
01:18:25.360 --> 01:18:41.199
campuses are. And finally, the air right subdist or air is where the highway and the on andoff ramps are. Um, this subdist is really unique in that it actually uses the same regulations as the neighboring R10 subdist, but it allows for PDAs, which will be essential

273
01:18:41.199 --> 01:18:56.400
in enabling any kind of development over the highway there in the future. Next slide. The R1 subdist is a primarily residential district mapped where there's an abundance of these legacy rowouses, including the Johnny Court

274
01:18:56.400 --> 01:19:11.360
area and between Tyler Street and Hudson Street. The zoning here represents a downzoning to protect these low-rise small-cale residential properties and some small-cale commercial activity there. For dimensional regulations, the maximum height is actually reduced from

275
01:19:11.360 --> 01:19:25.760
80 ft to 45 ft and a maximum building floor plate of 1,500 square ft helps to maintain the small building scale here. Yard requirements allow for the party wall condition of rowouses and allows for some minor additions to the rear of

276
01:19:25.760 --> 01:19:42.320
the properties. Next slide. The land uses focus primarily on residential units allowing anything under 15 units by right. Other small-scale commercial uses are made conditional like offices and social clubs to reflect that there are family

277
01:19:42.320 --> 01:19:58.880
associations and other nonprofits here that operate on different floors of these buildings. Larger, more impactful land uses are forbidden in the R1. Next slide. The CC subdist is mapped in the heart of Chinatown's commercial area primarily

278
01:19:58.880 --> 01:20:14.480
along Tyler Street, Hudson Street, Beach Street, and Harrison A. The regulations here are really aimed at making it easier for businesses to open and renovate and to maintain the smaller active storefronts that exist there today. The maximum building height here would be 80 ft, which is largely the

279
01:20:14.480 --> 01:20:29.679
same as today. And we're introducing a maximum building floor plate of 2500 ft. Um, this would allow for the consolidation and redevelopment of two typical small parcels. Next slide.

280
01:20:29.679 --> 01:20:46.400
Land uses here are aimed at maintaining the vibrant commercial activity of the area, particularly by allowing for restaurants, retail, and service establishments to occupy any floor of the building, which is a very common condition today. Residential uses are made conditional on the ground floor to promote a more

281
01:20:46.400 --> 01:21:01.360
active streetscape, and much larger uses like hotels, labs, and large offices would be forbidden. Next slide. The R10 subdist is mapped along the southern and eastern portions of the neighborhood where there are currently

282
01:21:01.360 --> 01:21:18.719
larger apartment buildings. The subdist better regulates these higher density residential areas, including recent development projects, and are designed to create better amenity space for both residents of these buildings and the broader community. One important thing to note here is that we had originally included an affordable

283
01:21:18.719 --> 01:21:34.640
housing overlay in our first zoning proposal, which would have allowed buildings to be taller as of right, provided they include a significant amount of affordable housing. However, the feedback we got around affordability levels and heights in our community conversations was extremely varied and

284
01:21:34.640 --> 01:21:50.000
often conflicting. So, reaching an appropriate consensus around uh the future of that um overlay was challenging. Instead, we anticipate that future projects may intend to exceed uh proposed zoning here and would only be approved through an article 80 process

285
01:21:50.000 --> 01:22:05.920
that includes extensive community engagement and support. Um that being said, for dimensions, a maximum building height of 155 ft brings some of these larger apartment buildings into compliance compared to today's 100t maximum. We've also included minimum

286
01:22:05.920 --> 01:22:21.520
outdoor amenity space and permeable area of lot to encourage better usable outdoor space for residents of any future buildings and the broader community. There are also required stepbacks above 70 ft where the project abuts um any historic buildings.

287
01:22:21.520 --> 01:22:38.719
Next slide. Residential uses are allowed throughout the subdist along with other supportive community serving uses like grocery stores and community centers. Um, other neighborhood amenities are either allowed or conditional on the ground floor like restaurants and retail and

288
01:22:38.719 --> 01:22:55.520
larger uses are made forbidden including hotels, labs, um, larger offices and entertainment and events. Next slide. The Skylow CT is mapped along Essex Street and really aims to maximize opportunities for the conversion,

289
01:22:55.520 --> 01:23:12.080
adaptation, and expansion of buildings. This is the first addition to the downtown historic dimensional overlay, which is exciting because it's an opportunity within zoning to acknowledge the cultural and historic significance of the buildings here. This area also previously had that affordable um

290
01:23:12.080 --> 01:23:27.600
housing overlay proposal that I mentioned before uh but has since been removed after our engagement conversations. The dimensions are the same as the sky low subdist that exists already in article 31 and the historic dimensional overlay limits the maximum height here

291
01:23:27.600 --> 01:23:45.440
to 155 ft. It also requires ground floor amenity space for larger buildings or larger properties um and has higher building lot coverage to reflect that existing context in Chinatown and the rest of downtown further to the north. Next slide.

292
01:23:45.440 --> 01:24:01.920
Again, the land uses here are already established as part of the SkyO district adopted into zoning last fall. Uh some key highlights are allowing for a greater mix of commercial activity and making larger uses like large hotels, offices, retail, and entertainment uh conditional use.

293
01:24:01.920 --> 01:24:18.719
Next slide. This last district is a bit unique in that we're actually creating a new um in institutional districts article uh separate from the Chinatown neighborhood article. This means that institutional districts um here could be mapped in other parts of the city later on as

294
01:24:18.719 --> 01:24:35.679
well. This IS-2 district is proposed to replace the existing institutional subdist in Chinatown under the TUS University IMP and the TUS Medical Center IMP. The IS-2 district is intended for denser urban environments where there are medical or academic institutions and

295
01:24:35.679 --> 01:24:50.400
mapped where there's a contiguous collection of institutional property within an IMP. Importantly, um, IMPPS will still supersede this new underlying zoning. In our conversations with institutions as part of this effort, it was incredibly important to restate this

296
01:24:50.400 --> 01:25:07.600
fact throughout the new zoning article. Um, however, this this will still make it easier, especially for small changes um to institutional properties that utilize the article 80 process rather than the IMP process for things like a change of use in the building. Um there aren't many uh dimensional

297
01:25:07.600 --> 01:25:24.400
regulations for the IS-2 district uh because any major redevelopment associated with an institution would go through the IMP or article 80 process and the lot coverage and building floor plate dimensions here are uh relatively high and the maximum building height of 300 ft better reflects the existing

298
01:25:24.400 --> 01:25:41.600
context of these large scale uh institutional holdings. Next slide. The institutional land uses not only allow for higher education and healthcare, but also some supportive uses that are often associated uh with campuses like retail, uh restaurants,

299
01:25:41.600 --> 01:25:57.040
grocery stores, and offices. We've also made residential uses allowed provided that any residential project goes through article 80. This was specifically a point of feedback from both the community and our institutional stakeholders. Conditional uses like um

300
01:25:57.040 --> 01:26:11.520
uh include large hotels and entertainment events um as well as research labs. Research labs could only be constructed here outside of the IMP context if the majority of the building is another use, not just an entire research building.

301
01:26:11.520 --> 01:26:27.280
Next slide. Another key change that we've made is adding more provisions around flood resilience. A large portion of Chinatown is within the coastal flood resilience overlay district or seafood. Uh the change here makes it so that no new residential units can be constructed

302
01:26:27.280 --> 01:26:42.000
below these flood elevation lines. So in many cases uh basements can't be converted into residential units. This will help improve the safety of our housing in the neighborhood. And this actually already applies for larger projects with at least 15 units.

303
01:26:42.000 --> 01:26:59.280
Next slide. And finally, the design guidelines. Um adopting the design guidelines as an amendment to plan downtown is a separate vote before you tonight. um and follow suit with downtown's design guidelines that were adopted last year. These guidelines serve as a tool for city

304
01:26:59.280 --> 01:27:15.760
staff, designers, developers, and the community to further shape projects based on historic context and offer clear guidance for enhancing the Chinatown neighborhood. In addition to specific guidelines, which I'll get into on subsequent slides, um we added a section here around family, village, and

305
01:27:15.760 --> 01:27:33.080
merchant associations in the neighborhood. These all have a significant historic current and future role in the community. So highlighting them in the design guidelines further supports their continued involvement in Chinatown going forward. Next slide.

306
01:27:33.600 --> 01:27:48.639
The guidelines emphasize finding adaptive reuse opportunities in the former textile buildings along Essex Street and they also suggest continuing the rhythm and scale of Chinatown's vibrant storefronts and facades. Next slide.

307
01:27:48.639 --> 01:28:04.800
They also highlight the significance of Chinatown's legacy rowouses dating back to the beginnings of the neighborhood. Also, as larger residential growth emerges in other areas of Chinatown, new projects should create community spaces and public realm improvements that the whole neighborhood can enjoy.

308
01:28:04.800 --> 01:28:20.880
Next slide. And finally, the guidelines also encourage projects to find opportunities for public art that highlights the history, culture, and voices of Chinatown. Next slide. >> Uh thank you all so much for your time

309
01:28:20.880 --> 01:28:36.639
uh and attention this afternoon. Uh happy to take any questions that you have. >> Thank you. Uh I'll read item number 16 and 17th off individually for individual votes. Uh item number 16 requests authorization to adopt an amendment to

310
01:28:36.639 --> 01:28:53.280
plan downtown that includes new Chinatown historic context design guidelines which will guide the BPDA in the community on the design development and review the projects that enhance Chinatown's unique and historic fabric. Uh are there any questions or comments

311
01:28:53.280 --> 01:29:09.920
from the board? >> Yes, thank you uh Mr. Chair. U Jack, thank you for that very thorough uh presentation. Obviously, I don't need to tell you. We all agree what a special important neighborhood Chinatown is. Wonderful people, wonderful businesses. Uh it makes perfect sense to do our own

312
01:29:09.920 --> 01:29:27.760
process for Chinatown as opposed to plan downtown. So, I'm with you on that. With you on virtually everything except one question that's sort of been stuck in my cross since we got wind of this. The the downsizing in R1 is fairly significant. Um, are we setting ourselves up, you

313
01:29:27.760 --> 01:29:43.440
know, at a distinct disadvantage when you and your colleagues and so many of us are spending so much time trying to fix well-meaning but but I would argue very restrictive aspects of the zoning code by purposefully downsizing. I know

314
01:29:43.440 --> 01:30:00.000
it's not a huge part of this plan. I understand sort of the the the you know iconic row houses, but also as we're removing uh residential from below ground, which is smart. I mean, we hear about gentrification, we hear about displacement, it seems to me that we're

315
01:30:00.000 --> 01:30:16.400
setting ourselves up for a disadvantage of potentially building more housing um in the neighborhood. >> Yeah, thank you for that. Um so, the rowhouse areas in Chinatown now constitute um about three blocks or so. Um, I would say they're mostly

316
01:30:16.400 --> 01:30:31.920
characterized by being a naturally occur occurring affordable housing in the neighborhood. And so there are, you know, pretty significant concerns from the community around displacement that could happen from um the development that that could happen in these areas if we were to upzone um or even keep the

317
01:30:31.920 --> 01:30:47.440
zoning as it is today. Um, you know, it is partly a preservation strategy to keep the character of the row homes. Um, but again, similar to the other parts of the neighborhood where I mentioned the affordable housing overlay, um, affordable housing is like really one of the key points in the planning document

318
01:30:47.440 --> 01:31:04.719
itself for plan downtown in Chinatown. Um, and so I, you know, we could imagine down the road, um, you know, article 80 projects always have the opportunity to apply for variances and go through the community process to get to that. Um, so, you know, on a project by project basis, I think we'd want to be able to

319
01:31:04.719 --> 01:31:19.840
evaluate that better um, in this area. Um, if you want >> I mean I mean I'm I'm going to vote for this. You haven't sold me. It sounds like though, you know, some of the the the things that we hear at community meetings.

320
01:31:19.840 --> 01:31:36.719
>> Yeah. I'll I'll also say that um this is a a great question and in many areas of the city, right, um we've started calling our zoning that while legally is an upzone a right size because the zoning so far below the existing buildings. In this instance, it's

321
01:31:36.719 --> 01:31:53.199
actually it's still a right sizing. The zoning is actually currently significantly above the existing buildings, and we're bringing that zoning envelope down to a size that reflects those existing buildings with a little bit of wiggle room to do an addition to to add a floor if you're

322
01:31:53.199 --> 01:32:08.080
losing basement space to floodproof your area. So, it's taking that same approach that we are taking in other areas where we're trying to make sure our zoning works for the existing context and structures in these areas where we're we're not envisioning significant

323
01:32:08.080 --> 01:32:23.520
growth. Um, legally that's a downzoning even though it's a right sizing in other areas of the city, right? We do that same right sizing that legally is an upzoning. That's just bringing it to that same baseline. >> Baseline right now is 80 feet. This

324
01:32:23.520 --> 01:32:38.560
would make it 45 feet. Correct. >> It's a significant reduction. I would argue the market has dictated that having a higher ceiling doesn't necessarily mean people take advantage of it. I mean I mean we could we could go round and round and sort of this >> I I totally hear you and I think this is

325
01:32:38.560 --> 01:32:54.880
also a really good example of exactly why this was a a two-year long community process with the need to come to some of these compromises is there right really really engaged community in Chinatown with really different opinions on what

326
01:32:54.880 --> 01:33:11.120
is the most appropriate for different areas of the the neighborhood and a sort of consistent agreement that like they're going to have to keep working together on each sort project or change that comes forward in order to continue to kind of keep Chinatown functioning as Chinatown in the city.

327
01:33:11.120 --> 01:33:26.719
>> Well, appreciate the appreciate the conversation. Thank you. >> Thank you. >> Definitely, Matt. Thank you for the question. Uh are there any other questions or comments? I would just say, you know, every one of these um district plans and zoning

328
01:33:26.719 --> 01:33:45.199
updates, you know, it it's obvious to us the the work that's reflected in, you know, kind of giving birth, literally just birthing each one of these plans and the uh the effort and dialogue that goes into it. I know it's um it is a

329
01:33:45.199 --> 01:34:01.440
neighborhood with very strong and not always agreeing opinions and so you know kudos to you guys for um landing something that I think will be a good a good template going forward. >> Yeah, that's two years and plus plenty

330
01:34:01.440 --> 01:34:16.800
more dialogue to go with that. So thank you. Thank you very much. So are there any other questions or comments? Seeing and hearing none, is there a motion on the floor? >> So moved. So second >> second. All in favor? >> I. >> Any oppose? Eyes have it. I will now

331
01:34:16.800 --> 01:34:33.679
read item number 17. Uh request authorization to adopt one text amendments for article 43 and article 8 to establish new Chinatown neighborhood district zoning regulations. And number two, text amendments for new article 34

332
01:34:33.679 --> 01:34:50.560
and article 8 to establish a new set of institutional zoning districts. three additional minor text amendments in article 2 3 23 2149A and article 89 to ensure consistency

333
01:34:50.560 --> 01:35:07.679
throughout the code and four map amendments to zoning map 1 CGN Chinatown district are there any questions or comments seeing and hearing none is there a motion on the floor >> so moved >> second >> second all in favor I

334
01:35:07.679 --> 01:35:29.199
>> any oppose eyes have it. Thank you. >> Thank you so much. Item number 18 requests authorization to petition the zoning commission to adopt text amendments which one implement updates to article 11 of the zoning code

335
01:35:29.199 --> 01:35:46.560
that establish new citywide zoning regulations for signs and two remove outdated signage regulations from the code. Cyrus and Lizzie floor yours. Good afternoon, Vice Chair Shepard, members of the board, uh, Director, Director

336
01:35:46.560 --> 01:36:02.320
Shen, and Secretary Pis. It's a pleasure to be here with you all today. Uh, my name is Cyrus Melli, and I'm a member of the urban design team here, and I'm joined by my fellow urban design colleague, Lizzie Turk, uh, to share a little bit about the department's sign

337
01:36:02.320 --> 01:36:19.440
code modernization initiative. Next slide. Sign code modernization is a project that ultimately seeks to make it easier for small businesses to put up new signage. Uh this is something that takes a significant amount of time. Now uh the

338
01:36:19.440 --> 01:36:35.040
project proposes to do this through three main goals. One, it seeks to update zoning to adopt appropriate but flexible rules that allow the vast majority of common everyday signs to be permitted by right. This will help expedite review and permitting for small

339
01:36:35.040 --> 01:36:51.520
businesses. Two, the project proposes to refine the applicability of planning department design review. While a buyight approval pathway is appropriate for many signs, it's not appropriate for all, especially those with outsiz visual impacts on the public realm. And three,

340
01:36:51.520 --> 01:37:07.960
we want these rules and processes to apply equally citywide to simplify process, improve accessibility to it, and allow for the development of different sign cultures to arise across the city organically. Next slide.

341
01:37:11.520 --> 01:37:26.880
This project has been important to pursue for many reasons, but one of them being that signage provides real value to our city and our communities. In addition to being a wayfinding guide or means to attract patrons to businesses, signs also represent an element of the

342
01:37:26.880 --> 01:37:40.639
built environment that reflects the history, identity, and expression of place. Accordingly, providing opportunities for unique and creative signs to take root is critical to creating streetscapes that are vibrant, textural, and reflective of the people

343
01:37:40.639 --> 01:37:59.280
that live and work there. Next slide. Sign code modernization initially launched in 2024. We held a public meeting introducing the project that March uh which was followed by a period of research, development, drafting, and internal testing. We began our interdep

344
01:37:59.280 --> 01:38:15.119
departmental coordination in 2025 and in 2026 moved to public process and now implementation. Our draft recommendations were released to the public almost two months ago and were accompanied by a public meeting to discuss in late March, four office hour

345
01:38:15.119 --> 01:38:32.080
sessions throughout April and a 45day public comment period ending May 1st. We received a lot of really helpful feedback from these comments, much of which was incorporated into our final recommendations. A public meeting discussing those uh was held last Thursday.

346
01:38:32.080 --> 01:38:47.920
Next slide. A disclaimer before we jump further into content. Uh due to first amendment rights and established legal precedent, it's important to note that the regulation and review of signage must focus on certain things. Things that the

347
01:38:47.920 --> 01:39:02.719
planning department can comment on and regulate include the size and location of signs, the types of the types of signs that are and are not allowed, and how signs may be illuminated. Things like the content of signs, such as

348
01:39:02.719 --> 01:39:18.800
language or logos, or the expression of that content, including through things like color, font, or imagery, are protected as expressions of speech and thus sit outside of our scope. The same applies to public art and murals. Now I'm going to pass it over to Lizzie

349
01:39:18.800 --> 01:39:33.760
to talk about some of the context of the project and some of our proposed recommendations. >> Thank you Cyrus. If you can advance the next slide, please to better understand why sign code modernization is needed, it's helpful to

350
01:39:33.760 --> 01:39:49.679
look at how sign rules and review works today. The majority of regulations are currently found in article 11 of the zoning code which was originally written in 1972 and since then almost no updates have been made. Its contents simultaneously under and overregulate

351
01:39:49.679 --> 01:40:05.119
signage in the city and are presented without a clear structure or hierarchy. In addition to article 11, the zoning code also lays out signage reg requirements in 25 other zoning articles. These requirements are also outdated and almost all all are between

352
01:40:05.119 --> 01:40:22.159
20 to 30 years old. They're hard to find and typically buried at the bottom of the relevant articles. Additionally, they frequently refer back to the provisions of article 11, which creates confusion as to what regulations apply, where, and when. Next slide, please.

353
01:40:22.159 --> 01:40:38.800
Due to these outdated uh regulations, today's signage review process has evolved to exempt ISD from code enforcement, leaving the review process in the hands of the planning department. Collectively, our team reviews about 900 signs per year via discretionary review

354
01:40:38.800 --> 01:40:54.000
process where size and placement is often negotiated instead of regulated. This takes time and we're often not the only entity who's reviewed is required. Because of this, permitting timelines, as we've heard from sign vendors and learned in our analysis, takes an

355
01:40:54.000 --> 01:41:09.920
average of 4.5 months to complete and oftentimes even longer. To fix this problem, we're proposing updated zoning and a review uh a revised review process for citywide um signs. Next slide, please.

356
01:41:09.920 --> 01:41:27.119
To inform our recommendations, the team um took an rigorous approach to research and analysis. The process included reviewing and collecting data on use, district, size, and types of sign for every single sign um every single approved sign package over the past 2.5

357
01:41:27.119 --> 01:41:44.560
to 3 years. We found to our surprise that there was almost no difference in the number, type or size of signs proposed across different business types and geographies. In addition, we reviews the existing sign codes of about 15 other peer um cities and analyzed

358
01:41:44.560 --> 01:42:01.679
several sign research publications. We also pursued several rounds of test fitting and modeling to help hone our requirements. Advance to the next slide, please. Based on these efforts, we landed on an approach that established four different categories of signs, each with their own

359
01:42:01.679 --> 01:42:17.520
rules um and associated review processes. That's allowed, conditional, forbidden, and exam sign types. Next slide. So allowed sign types represent the vast majority of the signs that we see in the city and are those that are most

360
01:42:17.520 --> 01:42:33.360
commonly associated with um the typical main street business. There are six types of loud signs as seen on the screen. Wall signs, canopy, projecting, window, awning, and freestanding signs. Um, and article 11 establishes appropriate but flexible dimensional

361
01:42:33.360 --> 01:42:48.080
requirements and illumination controls for these sign types. Unlike today, allowed signs will still undergo an administrative review at ISD and if compliant may be permitted by right without design review. We anticipate 80

362
01:42:48.080 --> 01:43:03.840
to 85% of allowed signs to be compliant with these new rules and to be able to be permitted within 30 days. allowed signs that are non-compliant with the code would need to go to the ZBA for a conditional use permit. I'm going to hand it back to Cyrus um to further

363
01:43:03.840 --> 01:43:22.320
explain these impacts on the next slide. Thank you. Um reestablishing an administrative review and approval pathway for everyday signs will have a significant impact on increasing permitting speeds and advancing permitting reform. Um, in fact, we

364
01:43:22.320 --> 01:43:39.679
anticipate these updates uh to reduce the time to permit for small business signs by roughly 80% from existing. And when you extrapolate that across all proposals, that reduction equates to nearly 100 years of cumulative sign permitting time saved annually. The

365
01:43:39.679 --> 01:43:57.760
saves small businesses valuable time and money, but also by simplifying review helps ISD and public works standardize the enforcement of science. So, a win-win there. Next slide. While this expedited review is great for most signs, the planning department

366
01:43:57.760 --> 01:44:14.719
recognizes that some, like conditional signs, need additional review because of their outsized impacts on the public realm. Conditional conditional signs will require both planning department design review as well as a conditional use permit from the ZBA, a stricter standard than what currently exists for

367
01:44:14.719 --> 01:44:32.080
most. The signs that are applicable to this type of review are high building signs, roof signs, marquees, and electronic signs for entertainment and hospital uses. Next slide. Forbidden signs constitute an even

368
01:44:32.080 --> 01:44:47.440
smaller percentage uh of these signs and are defined as those uh excessive in scale or with potentially harmful impacts on the public realm. They include the signs that you see on your screen. Um, and such signs would only be allowed to be permitted after obtaining

369
01:44:47.440 --> 01:45:03.840
a variance from the ZBA. Next slide. To ease the transition and improve accessibility to this new process, we also intend to supplement the article 11 updates with a how-to guide that explains the permitting process and clearly walks through the types of

370
01:45:03.840 --> 01:45:22.880
review and submission requirements for obtaining a permit. Additionally, we're developing new design guidelines that will explain best practices and encourage quality design for science. Next slide, please. Um before we wrap up, I just want to

371
01:45:22.880 --> 01:45:39.199
take a moment to acknowledge our interdep departmental partners and coordination uh which was a hugely valuable part of our vetting process, especially in refining our recommendations revolving around updates to permitting and the streamlining of review. Um as you can see, there are a lot of actors that are involved uh in

372
01:45:39.199 --> 01:45:55.639
signage review. Um advancing this project really wouldn't have been possible without their collaboration and support. Um, and we're grateful for the guidance and help that they've provided us in helping to move this along. Next slide.

373
01:45:57.199 --> 01:46:14.159
Looking ahead, we anticipate the implementation of sign code modernization to occur midsummer. Uh, this sets us up to see and study some initial returns in the fall. Uh, we want to make sure that we're doing what we're setting out to uh to help ease the transition of review responsibilities.

374
01:46:14.159 --> 01:46:30.960
uh planning department staff are also going to be providing ISD with support at both intake and in review uh from adoption through the winter. And our supplemental materials, as Lizzie mentioned, which include uh both new submission requirements and the how-to guide, are expected to be rolled out and

375
01:46:30.960 --> 01:46:48.000
socialized alongside the implementation of our zoning. Next slide. And with that, we'll close out. Thank you very much for your time and Lucy and I are available to answer any questions that you may have. >> Thank you. Thank you for the presentation. Are there any questions or

376
01:46:48.000 --> 01:47:03.520
comments from the board? >> Uh thank you, Mr. Chair. So just to be clear, wacky waving inflatable arm flailing tube man will not be allowed. >> Uh un unfortunately not. >> I would not. Very good. No, I I think this is great. How many So the original

377
01:47:03.520 --> 01:47:20.960
um uh code had 16,000 words 50 years ago. How many words will this have? >> Uh 4,500 that are all going to be located in a single article in the code and cover about twice the amount of material. >> Perfect. No, this is great. And listen, I I uh anything we can do to streamline

378
01:47:20.960 --> 01:47:38.239
processes like this, the better. I would just say, and I I think we all agree with this, going through the deck, there were so many iconic Boston signs that we love and we don't want to lose that. And so I just hope that that's um and I don't think it's the case, but I hope as we talk to these businesses who may make

379
01:47:38.239 --> 01:47:54.320
a decision about something quick and easy or something maybe a little more um nuanced, but we'll have that, you know, the cow head at JP Licks, the you know, the the bulling, the the modern pastry. So many great signs um that we we don't we don't do anything to dissuade those because they are such an important part

380
01:47:54.320 --> 01:48:10.560
of our city's character. >> 100 100%. Thank you. Are there any other questions or comments? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> All in favor? I >> I. >> Any oppose? Eyes have it. Thank you.

381
01:48:10.560 --> 01:48:28.239
>> Thank you very much. Item 19, request authorization to issue a certificate of completion for the successful completion of the 1595 through 1599 Columbus A project pursuant of section C4 of the cooperation

382
01:48:28.239 --> 01:48:44.000
agreement by by and between the Boston Redevelopment Authority doing business as Boston Planning and Development Agency and the 1595 through 1599 Columbus Awner LLC. dated April 22nd,

383
01:48:44.000 --> 01:49:00.159
2022. Uh this is assert of completion. No presentations. Are there any questions or comments? Seeing and hearing none. Uh is there a motion on the floor? >> So move. >> Second. >> There's a second. All in favor? >> Any oppose? >> Eyes have it.

384
01:49:00.159 --> 01:49:16.960
Item number 20, request authorization to issue a certificate of completion for the successful completion of 200 Cort Boulevard project, also known as the Commonwealth Pair Revitalization Project pursuant of section C4 of the

385
01:49:16.960 --> 01:49:32.480
cooperation agreement with by and between the Boston Redevelopment Authority doing business as Boston Planning and Development Agency and Commonwealth Payer Trust. to the proponent dated September 15,

386
01:49:32.480 --> 01:49:47.840
2020. Another um certificate of completion. Are there any questions or comments? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> There's a second. All in favor? >> Any oppose? Eyes have it. Thank you.

387
01:49:47.840 --> 01:50:03.760
Item number 21, request authorization to issue your certificate of completion for the successful completion of improvements on parcel J-1 in the downtown waterfront Faniel Hall urban renewal area project number mass R-77

388
01:50:03.760 --> 01:50:19.840
located at 150 Milk Street pursuant to the section 304 of the land disposition agreement by and between the bar and the Jenny building associates limited partnership dated 20, excuse me, May

389
01:50:19.840 --> 01:50:35.440
20th, 1983. Are there any questions or comments from the board? Seeing hearing none, is there a motion on the floor? >> So moved. >> Second. >> There's a second. All in favor? >> I. >> Any opposed? Eyes have it.

390
01:50:35.440 --> 01:50:50.719
Item number 22, request authorization to issue a determination waving the requirement of further review pursuant to section 8A-6 of the zoning code in connection with the notice of project change submitted

391
01:50:50.719 --> 01:51:08.719
on March 16th, 2026 by Brainree 90 Alton LLC for the construction of 111 residential rental units including 14 IDP units and eight voucher units. 50 58 car parking spaces and 111 bicycle

392
01:51:08.719 --> 01:51:25.040
spaces located at 90 Bray Street. And number two, issue a certificate uh certification and compliance under the section 80B-6 of the code upon success successful completion of article 80 review process

393
01:51:25.040 --> 01:51:41.040
and three enter into a affordable rental housing agreement and restriction cooperation agreement and transportation action plan agreement in connection with the proposed project and take all related actions. So,

394
01:51:41.040 --> 01:51:56.560
>> good afternoon, Chair Shepard, members of the board, Secretary Poheimis, and Director Shen. My name is Zoe Duval, and I'm a project manager in development review. I'm here before you to present the expedited notice of project change for the 90 Brain Tree Street project.

395
01:51:56.560 --> 01:52:12.719
Next slide, please. Originally approved on March 10th, 2022, this project is approved to include a new six-story residential building containing 111 rental units with 22 affordable units, 59 garage parking spaces, 111 bike

396
01:52:12.719 --> 01:52:29.520
parking spaces, artist workspace, and 9,500 ft of usable open space. The proposed projects changes. The proposed project change seeks to remove the below grade parking component of the previously approved project and replace all 59 spaces with a first floor stacker

397
01:52:29.520 --> 01:52:46.800
system. A change which would result in reorientation of the unit mix floor plans and green space with slight massing and penetration changes to accommodate the adjustment. The originally approved unit count of 111 rental units will remain along with the originally approved 111 resident bike

398
01:52:46.800 --> 01:53:02.320
parking spaces, 22 visitor bike parking spaces, and open space square footage. All of the previously approved mitigation and community benefits items will remain and include monetary contributions to the Alustin Brighton CDC, the parks department for allocation

399
01:53:02.320 --> 01:53:18.880
to the abuing Pinnaman Park, and bike share and bike lane improvement contributions. Next slide, please. The proposed removal of the subgrade parking would result in the previous 10 loft units to be replaced with a mix of studio and one-bedroom units, resulting

400
01:53:18.880 --> 01:53:36.320
in an updated unit mix of 52 studios, 49 one beds, and 10 two beds. The previously proposed three-bedroom units were removed as part of this proposal. Additionally, the proposal includes a revision of the affordable unit breakdown to include 14 inclusionary

401
01:53:36.320 --> 01:53:52.800
development policy units and eight voucher units in replacement of the previously proposed 22 IDP units of which five were designated as artist live workspaces. On March 16th, 2026, the proponent, the new proponent and six properties filed a notice of project

402
01:53:52.800 --> 01:54:08.960
change under expedited review for the proposed changes. The filing initiated a 30-day comment period that concluded on April 15th after the filing was distributed to the IAG and to the Backbay neighborhood distribution list and posted on the planning department's project web page. A public meeting was

403
01:54:08.960 --> 01:54:24.960
to be held at the request of public officials. No public meetings were requested or held for the project changes. Thank you. And that concludes the presentation. The development team is also here to answer any questions you may have. >> Thank you. Are there any questions or

404
01:54:24.960 --> 01:54:42.719
comments from the board? >> Hearing and seeing none. Is there a motion on the floor? >> So moved. >> Second. >> Second. All in favor? >> I >> I. >> Any oppose? Eyes have it. Thank you. >> Yes. Item number 23, request

405
01:54:42.719 --> 01:54:58.480
authorization to one issue certification of approval for the proposed development located at 419 Boilston Street pursuant to article 80 small project review of the zoning code and two enter number two

406
01:54:58.480 --> 01:55:14.000
enter into a pilot agreement and number three adapt adopt uh demonstration project plan under the Massachusetts General Law Chapter 121B section 46. 6F and number four adopt certain findings

407
01:55:14.000 --> 01:55:29.599
relating to the demonstration project plan and number five accept a quiet claim deed for certain temporary limited property interest in the project site and to take all related actions. Zo,

408
01:55:29.599 --> 01:55:46.239
>> thank you. Good afternoon again. I am here before you to present an applicant of Mayor Woo's office to residential conversion program, the proposed article 80 small project located at 419 Boilston Street in the Backbay neighborhood of Boston, and the proposed 121B agreement

409
01:55:46.239 --> 01:56:03.119
to effectuate the residential conversion incentive pilot program. Next slide, please. On August 29th, 2025, Monarch Development, the proponent, applied to Mayor Woo in the BPDA's downtown residential conversion incentive pilot program authorized by

410
01:56:03.119 --> 01:56:18.719
the BPDA board on October 12th, 2023. Based on BPDA staff review under article 80 and under review and review under the pilot program, the proponent has been selected to receive a pilot agreement based on the pilot program criteria. The

411
01:56:18.719 --> 01:56:36.239
proponent will upon approval by the BPDA board enter into a pilot agreement among the city of Boston and the BPDA. In order to comply with the rules and regulations under Massachusetts General Law, Chapter 121B section 16, the BPDA must take a property interest in the

412
01:56:36.239 --> 01:56:52.080
project site. On January 13th, 2026, the proponent filed a small project review application submission submission of which initiated the small project review. The planning department hosted a virtual public meeting on January 26, 2026, which was well attended and

413
01:56:52.080 --> 01:57:07.280
wellreceived. The public meeting was noticed on the planning department's events calendar and sent to the Backbay neighborhood distribution list. The comment period ended on March 14th, 2026. The project site is located on the north

414
01:57:07.280 --> 01:57:22.400
side of Boilson Street between Berkeley Street and Arlington Street and is well served by multiple public transportation options. The site currently consists of an 8-story 48,45 gross ft vacant office building with vacant retail space on the first and

415
01:57:22.400 --> 01:57:41.119
second floors. The proposal seeks to retain the existing retail uses on the first and second floors. Next slide, please. and convert the vacant office floors into 41 residential rental units consisting of 27 studio units and 14 one-bedroom units

416
01:57:41.119 --> 01:57:58.639
in approximately 37,385 square ft of gross floor area. The proposed project will also contain 43 resident bike parking spaces in the basement and four on the first floor with eight exterior visitor bike parking spaces. The proposed project will preserve the existing building envelope,

417
01:57:58.639 --> 01:58:14.400
structural system, and primary facade openings. The proposed project scope is limited to interior work with the combined buildings with the combined with the building at the site with no expansion to its existing footprint or facade. Thank you. And that concludes the presentation. Again, the proponent

418
01:58:14.400 --> 01:58:31.040
team is also here to answer any other questions you may have. >> Thank you. Are there any questions or comments from the board? >> I have a quick question. And I I love these conversion projects, all four of them. But in this one, the um units are

419
01:58:31.040 --> 01:58:48.560
disproportionately studios. Typically, they're a little more proportional to the to the mix generally of the building. Is there a reason for that? >> Um I think we went back and forth with a few different unit mixes. I know the the

420
01:58:48.560 --> 01:59:13.679
project team is here and I can defer to them for um maybe an explanation of why they went a certain route. >> Hi Mark Alinkar um president of MP Design Consultants. Um the reason for that was just to maximize the number of

421
01:59:13.679 --> 01:59:30.159
units to for the building and also how the building is shaped in a rectangular manner. To maximize that you would almost have to put the layout four four units in the front of the building facade and four in the back cuz you also have to make sure to balance out the um

422
01:59:30.159 --> 01:59:45.199
real estate of the windows and make sure that you're all up to code. So that was mainly the reason to maximize the number of units given, you know, the housing issues that we're all aware of. >> Okay. I I I guess just a general

423
01:59:45.199 --> 02:00:02.000
comment. I don't want to hold this pro project hostage over it, but I I think be typically it seems like the department does a really good job of ensuring that there's a fairly similar distribution with the affordable units. And so I think we just want to watch for

424
02:00:02.000 --> 02:00:17.520
that with these with these projects. Thank you. >> You have questions and comments. Uh for myself, I would just say I can we all can see that uh office to residential is um explo it's exploding at a good rate

425
02:00:17.520 --> 02:00:32.400
and we're very happy to see that. Um all I would ask is that during the construction we use responsible contractors. Um and definitely, you know, with the historic tax credits and things, maybe not on this project, but on other projects similar. Um again,

426
02:00:32.400 --> 02:00:48.239
just responsible contractors is key. Um these are unique areas of Boston that um are having the ability to transform and we just like to keep responsible contractors and the um chance for young men and women that come out of trade

427
02:00:48.239 --> 02:01:03.599
schools to be a part of it through the apprenticeship program. So, thank you very much. Y Are there any other questions or comments? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> Second. All in favor? >> I.

428
02:01:03.599 --> 02:01:23.520
>> Any oppose? Eyes have it. Thank you. >> Take a break and then >> can we? I would love to. >> All right, we're going to take 10 minutes. No, five minute recess. >> I like this chair.

429
02:01:23.520 --> 02:12:46.800
You don't know. You don't know. This is a public hearing before the Boston Redevelopment Authority doing business as the Boston Planning and Development Agency being held in the conference room with article 88-2 and

430
02:12:46.800 --> 02:13:03.599
ADC-5 of the Boston Zoning Code to approve the proposed phase 2 building C development plan for plan development area number 94 Bartlet Place, Barlet Station and Bartlet Drive in the Nubian Square area of Roxbury.

431
02:13:03.599 --> 02:13:20.239
The hearing was duly advertised on April 28th, 2026. This is a BPDA hearing on a proposed petition by the agency staff. Members will first present their case and are subject to questioning by the members of the agency. Thereafter,

432
02:13:20.239 --> 02:13:35.040
anyone who wishes to testify about the proposed project will be afforded the opportunity. We are taking support in opposition. At the same time, if you are planning to testify via Zoom,

433
02:13:35.040 --> 02:13:51.119
please take the time now to verify that your computer microphone is active and click the hand icon on your Zoom control panel. This will signal to the staff that you would like to speak. When your hand ra When your hand is raised, it will be

434
02:13:51.119 --> 02:14:08.560
blue. If you're calling in into the meeting, you would and like to testify, please dial star9 to raise your hand. When I call for all testimony, staff will announce your name and allow you to talk. You must unmute your mic. Your webcam will not be active. If you are

435
02:14:08.560 --> 02:14:25.360
planning to testify in person in the boardroom, please line up behind the podium after the presentation has been concluded and you will be called upon. In an effort to accommodate all who would like to speak about this proposal, each person will be given up to two

436
02:14:25.360 --> 02:14:39.840
minutes to comment. BPDA staff will indicate when 30 seconds remain. At the time, please conclude your remarks so that the hearing may continue and others may be heard. Finally, the proponents are allowed a period of 5 to 10 minutes

437
02:14:39.840 --> 02:14:57.440
to rebuttal if they desire. Open public meeting law requires that we ask if there is anyone in the audience who is recording this meeting. If you are recording this meeting, please identify yourself now. Uh one second, Jason, before you start

438
02:14:57.440 --> 02:15:13.760
the presentation, I would also like to say um let's not have any um what is it? demonstrations of approval or disapproval during the presentation and during this meeting. So Jason, the floor is yours. >> Thank you, Chair Shepard, members of the

439
02:15:13.760 --> 02:15:30.159
board, Secretary Bohemis, and Director Shen. My name is Jason Frell, and I'm a project assistant with the development review division at the planning department. I'm here today to discuss the Bartlett Station project, also known as Bartlett Place Lot C project, and the

440
02:15:30.159 --> 02:15:47.360
associated PDA development plan titled phase 2, building C, located within the previously approved PDA number 94, also known as Bartlet Place Master Plan in the Nubian Square area of the Roxberry neighborhood. The proposed development

441
02:15:47.360 --> 02:16:02.719
at Bartlett Station is the only project within um the phase 2 building C development plan. The development plan and project propose construction of a four-story building containing 61 mixed income home ownership units of which 12

442
02:16:02.719 --> 02:16:17.119
are income restricted and four are dedicated to artists live work. The building will include a below grade parking garage with 51 spaces and other rental residential amenities including but not limited to 61 long-term and

443
02:16:17.119 --> 02:16:34.719
short term 61 long term and 14 short-term bike spaces. Um a private inter courtyard and gallery space for artist use. The project notification form was filed on November 18th, 2025 initiating a 30-day comment period. and

444
02:16:34.719 --> 02:16:49.920
the associated development plan was filed on December 22nd, 2025, initiating a 45day comment period. The project and development plan were reviewed under the article 80 review procedures laid out in sections ADB and ADC of the code. The

445
02:16:49.920 --> 02:17:04.719
planning department hosted meetings with the Bartlet Place master plan project review committee on December 17th, 2025 to discuss the large project and January 17th, 2026 to discuss both filings. The planning department hosted a public

446
02:17:04.719 --> 02:17:20.399
meeting on January 6th to discuss both filings. Furthermore, the project was considered by the Boston Civic Design Commission on um also known as BCDC on February 3rd, 2026 and the BCDC design subcommittee on

447
02:17:20.399 --> 02:17:41.599
March 24th, 2026. The project was approved by BCDC on May 5th, 2026. I will now turn it over to For Delvecio for a presentation on planning and zoning contexts for the project. Thank you, Jason. Uh,

448
02:17:41.599 --> 02:17:56.880
perfect. Uh, the project site is situated entirely in plan development area 94 identifi plan development area 94 identified in the master plan as Bartlett Place phase 2. The site is designated for up to 61 dwelling units and accessory parking within a structure

449
02:17:56.880 --> 02:18:12.960
limited to 110,000 square feet of gross floor area and a height of 50 feet. The currently proposed project remains within these established regulatory parameters. Geog geographically, Bartlett Place serves as a vital link between the Nubian Square business district and the residential communities of Highland Park, St. James, and St.

450
02:18:12.960 --> 02:18:28.719
Joseph. The site's former use as a transit yard historically created a significant void in the urban urban landscape, disrupting the continuity of the neighborhood and leaving a vacant gap along Washington Street as exemplified in the larger picture. The Rosbury strateg strategic master plan uh in the picture in the bottom right notes

451
02:18:28.719 --> 02:18:44.639
that the area of Washington Street should be developed with an emphasis on renitting the neighborhoods on either side of it. Residential and or mixeduse development should be considered here. The proposed project along with earlier phases of the master plan repairs this urban fabric by introducing active mixed-use buildings along Washington Street while transitioning to smaller

452
02:18:44.639 --> 02:19:01.439
scale town houses along Bartlett Street, Guild Street, and Lambert Avenue to better reflect the surrounding residential context and reinforce the goals outlined within the Roxberry strategic master plan. Thank you. And I will now hand it off to Mike Ross to describe the plan in more detail. >> Good evening, Madam Secretary, Mr.

453
02:19:01.439 --> 02:19:18.639
Director, Mr. Chair, uh members of the board. My name is Mike Ross. I'm an attorney at the law firm of Prince Low Bell and I'm here today uh online with architect uh Nejis Bubanellis and consultant Beverly Johnston. Um we would

454
02:19:18.639 --> 02:19:34.960
like to thank the project managers Jason Farrell and Camille Platt D Costa for their strong and consistent professional approach to our project. We would also like to thank the project review committee that worked with us on this, the Roxberry community, the civic

455
02:19:34.960 --> 02:19:51.840
design commission and his very capable staff for working with us throughout the process. We represent a familyrun development team uh where its founder Nelson D. Ala arrived in the United States uh just decades ago with $50 in

456
02:19:51.840 --> 02:20:08.560
his pocket. uh he built this development um pro uh group with his now with his son um from the ground up and uh in addition to this project that's in front of you today, he is completing a 37 home

457
02:20:08.560 --> 02:20:25.840
ownership building, building four uh on this site and is in the final stages of permitting 28 home ownership projects also on this site. Um what you're looking at here, as previously described, Barlet Yards and

458
02:20:25.840 --> 02:20:41.280
and our proposed building, building C now called um Bartlett Station, uh is this longheld community vision uh that the leaderships of the city, the community of Roxberry, Newest Communad, and others helped bring to fruition.

459
02:20:41.280 --> 02:20:58.560
We're proud to be here today to offer this latest proposal, Bartlett Station uh which will represent the full uh permitting of this 8.59 acre uh and and virtually uh the majority of it which has been constructed. Uh the next slide

460
02:20:58.560 --> 02:21:15.359
uh shows Bartlett Station uh on its 39,273 square foot vacant lot. Uh it will be comprised as mentioned 61 mixed income home ownership units. 12 of them are affordable. That's 20 20%. Uh and there

461
02:21:15.359 --> 02:21:32.160
will also be four artists live work units uh in the site. Uh there's a gallery. There's 51 parking spaces and 62 bicycle spaces. Next slide please. Um the project actually one more slide

462
02:21:32.160 --> 02:21:49.920
if you don't mind. Thank you. Thank you. Uh the project undulates in height from three to four stories above grade depending on the building itself but also the topography of the land. Uh in that the land slopes down one story uh

463
02:21:49.920 --> 02:22:06.240
from Bartlett Station Drive which is the front door of the building. What you're seeing there is the courtyard side of the building and that's a full story below Barlet Station Drive. So the topography kind of helped uh direct some

464
02:22:06.240 --> 02:22:22.479
of the building programming itself. Uh in addition to the open space with with the courtyard on the left wing of uh of the building from what you're seeing there uh there is a roof deck uh above

465
02:22:22.479 --> 02:22:37.520
that and uh it's connected to a building amenity, you know, and these are home ownership units as well. So that will provide some great outdoor space for the residents who who own their units and live in the live in the building. Next slide, please.

466
02:22:37.520 --> 02:22:54.800
This section shows the kind of spanning more than just the building site. This section shows the topography of the entire uh site itself. Uh the next slide shows the uh

467
02:22:54.800 --> 02:23:10.240
height differential from the uh front of the building on the left to the rear of the building or the other side of the building on the right. And then just one other slide just showing a section just to give you a feel of the of the building and what you

468
02:23:10.240 --> 02:23:27.200
what you have there. Next slide please. These elevations show the facades and materiality of the four main sides of the building. Uh the top elevation shows the main entrance side of the building. That's the Bartlett station uh side of the building. Uh with the main

469
02:23:27.200 --> 02:23:44.319
residential entrance is it's on the left and and you can see the brick masonry uh three floors above it. That is that is the main entrance of the building. And then in addition to these masonry materials that you see in that darker color and that burgundy color, the

470
02:23:44.319 --> 02:24:01.200
remaining materials would be cemented cementitious laps siding, some sort of cementbased laps siding. Uh and they're shown they're shown on the slide there as well. Next slide, please. Uh this is a shot from coming from Washington Street uh on Bartlett Station

471
02:24:01.200 --> 02:24:16.560
and uh uh and and you can see the building ahead with that roof that left wing roof deck wing uh that you're looking at on the right there. Next slide, please. Uh so this is a view of the side of the building as you make

472
02:24:16.560 --> 02:24:32.720
your way up towards Bartlett Station Drive. Um, it shows the you can see the roof deck there on the right and then on the left that's the corner is where the gallery is. In the next slide you can it's a better shot. It's a shot from

473
02:24:32.720 --> 02:24:48.960
that corner and that's where that gallery is. And the gallery will be used for a gallery but it can also be used for different staging and public you know different kind of public facing events and that kind of thing. Uh the next slide. Uh so now we're moving to the other corner of Bartlett Station

474
02:24:48.960 --> 02:25:04.960
Drive. It's the corner of Bartlett Station Drive and Bartlett Street. And and then that main entrance there on on the right to the right of that main mass there and the darker masonry material. Uh next slide. And we are back here now

475
02:25:04.960 --> 02:25:20.640
at the courtyard side of the building. And that corner there is where the garage entrances, the garage entrance to the 51 parking spaces. And then finally, this last slide here. Uh this is just finishing at kind of an evening shot of the main entrance of the building on

476
02:25:20.640 --> 02:25:37.520
Bartlett Station Drive. And uh that's what I have for you today. I'm happy to answer any questions if you have any. Thank you. Thank you for your time. >> Thank you. Uh this is a public hearing and we will now take public testimony. If you would like to testify in person, please step to the podium and announce

477
02:25:37.520 --> 02:25:53.040
your name, affiliation, and your position on the proposed project when you are called to speak. If you are Zoom and you would like to testify, please raise your virtual hand. >> Thank you, Mr. Chairman, members of the board, Madame Secretary, Director Shane,

478
02:25:53.040 --> 02:26:11.120
Minor Perez here representing the Carpenters Union. We like to go in regular support of this project. Thank you. >> Good evening, members of the board. Um, my name is Daniel Daly. I'm a lifelong Boston resident and I'm also a business representative for local 103 uh with the

479
02:26:11.120 --> 02:26:26.800
electricians union. Boston needs housing and our residents need jobs. And this is a perfect example of how that's uh can get done with contractors that respect the Boston residency job policy and support the men and women who live in Boston and support our small businesses

480
02:26:26.800 --> 02:26:48.760
and vote in our election. So, I want to go on record in support of this project. Thank you. Is there anybody online who would like to testify about the Bartlett yard project? Please raise your virtual hand.

481
02:26:51.280 --> 02:27:08.000
>> Chair, there's no one online to testify. >> Thank you very much. Uh do any of the board members have any questions or comments? >> Yes. Thank you, Mr. Chair. Um and Councelor Ross, thank you for that great overview. I think it's a testament to the support of this project that there is such little chatter online. I

482
02:27:08.000 --> 02:27:24.319
certainly support it. We'll be voting in favor. I think it's a good-looking building. Um appreciate the commitment to affordability. Uh quick questions. Are the with the 20% um income restricted units. Does that include the four artist lofts or is that separate? >> It's a great question. U it it includes

483
02:27:24.319 --> 02:27:41.439
one of the four artist lofts. Uh there's a a matrix of it. Uh but it was it was one of the discussion points that we went through with with staff and I think initially it wasn't but then we brought one in. >> Okay. I think that's that's fantastic. Um and

484
02:27:41.439 --> 02:27:57.520
uh obviously love love the sustainability piece. Electric heat pumps, high energy. Um I love the roof deck too. So I'm not the question I'm not including the roof deck, but you've got a fourth level. Is there it's obviously pre-wired for PV panels. Is there been any thought about installing

485
02:27:57.520 --> 02:28:14.080
some photovoltaics on top? >> That's a good question. We did have a conversation about it. Um I think Nerius could probably answer that better than I could. Um because I'm not entirely sure where we where we landed on that. I can tell you that that roof deck that we have is on

486
02:28:14.080 --> 02:28:28.880
the third floor above that wing and then the rest of the uh top of that building is all for mechanicals and it would be completely appropriate for the photo photo tag. So I don't know how you would get near to

487
02:28:28.880 --> 02:28:45.359
zoom in here. There he is. >> Y >> thank you. >> Good evening. Good evening members of the board. Good evening guests and team. Um so to answer the uh Nalis from KDI architects in summer. Uh thank you. uh to answer that question is uh I don't

488
02:28:45.359 --> 02:29:01.200
know if there's full commit commitment yet done uh by the by the owner for the for the voltage but it will also depend on the on the uh down the process and uh with the passive house consultant uh

489
02:29:01.200 --> 02:29:16.640
model modeling see how we are with the generation but >> we have a full upper roof available for for for PDS so it it will be determined I'm glad to hear you're having the conversations. I'd urge you to uh go

490
02:29:16.640 --> 02:29:32.080
beyond that. I mean, h having these these these incredibly efficient heat pumps to marry that with some on-site renewable generation is going to be enormously attractive to residents and obviously lower the footprint and go above beyond. So, I think it's I think it's a great opportunity and glad to

491
02:29:32.080 --> 02:29:48.000
hear the conversations will continue. Um, thank you. >> I'll pass your uh recommendation along to our team. Thank you. Okay. >> Are there any other questions or comments? Seeing and hearing none. Is there a motion on the floor? >> So moved. >> Second. >> Second. All in favor? I.

492
02:29:48.000 --> 02:30:14.720
>> Any oppose? Eyes have it. >> Thank you very much. Have a great night. >> All right. This will be our sec um second public hearing. This is a public hearing before the Boston Redevelopment Authority doing business as the Boston Planning and

493
02:30:14.720 --> 02:30:31.840
Development Agency being held in the conf conformance of the Massachusetts General Laws Chapter 121A and the Acts of 1960, Chapter 652, each as amended in article 80B, large projects review of

494
02:30:31.840 --> 02:30:49.439
the Boston Zoning Code to consider the proposed 121 1A application filed by the Weston Library Preservation Associates LLP and to one adopt the adopt a report and decision on the Weston Library project located at 151 Cambridge Street

495
02:30:49.439 --> 02:31:06.240
in the Boston's Weston neighborhood. Two, issue a scoping determination waving further review pursuant to article 80B large project review of the zoning code for the West End library 121A project and three issue uh

496
02:31:06.240 --> 02:31:22.479
certification of compliance under the section 80B-6 of the code upon successful completion of the article 80 review process and four enter into into a cooperation agreement. This hearing was duly

497
02:31:22.479 --> 02:31:39.600
advertised on April 28th, 2026. This is a BPDA hearing on proponents on proposed petition, sorry, by the agency. Staff members will first present their case and are subject by into questioning by the members of the agency.

498
02:31:39.600 --> 02:31:57.359
Thereafter, anyone who wishes to testify about the proposed project will be afforded an opportunity. We are taking support and opposition at the same time. If you're planning to testify via Zoom, please take the time now to verify that

499
02:31:57.359 --> 02:32:12.240
your computer microphone is active and click the hand icon on your Zoom control panel. This will signal to staff that you would like to speak. When your hand is raised, it will be blue. If you are calling into the meeting and would like

500
02:32:12.240 --> 02:32:28.000
to testify, please dial star9 to raise your hand. When I call for all testimony, staff will announce your name and allow you to talk. You must unmute your microphone. Your webcam will not be active. If you are planning to testify

501
02:32:28.000 --> 02:32:42.640
in person in the boardroom, please line up behind the podium after the presentation has been concluded and you will be called upon. and an effort to accommodate all who would like to speak about this proposal. Each person will be

502
02:32:42.640 --> 02:32:58.960
given up to two minutes to comment. BPDA staff will indicate when 30 seconds remain. At that time, please conclude your remarks so that the hearing may continue and others may be heard. Finally, proponents are allowed a period of 5 to 10 minutes for rebuttal if they

503
02:32:58.960 --> 02:33:15.439
desire. Open public meeting law requires that we ask if there's anyone in the audience who is recording this meeting if they if you are recording this meeting can you please identify yourself with that. Thank you Kim.

504
02:33:15.439 --> 02:33:30.160
>> Thank you Vice Chair Shepard. Good evening members of the board director Shen and Secretary Paulus. My name is Camille Platiccasta and I'm a senior project manager here. The proposed 121A project before you is an article 80 large project located at 151 Cambridge Street in the west end. also known as

505
02:33:30.160 --> 02:33:45.439
the West End re library redevelopment project. Preservation of affordable housing inc also known as POA and Cass Capital proposed to demolish the existing library building to construct a new mixeduse two-story branch library and approximately 119 incomerestricted

506
02:33:45.439 --> 02:34:02.000
rental residential units across an additional 12 stories. The residential unit mix will range from studio to three-bedroom apartments with units available for families, seniors, and individuals earning less than 80% of the area median income. The new two-story branch library will be more than double

507
02:34:02.000 --> 02:34:18.960
the size of the current library and the design of the space will be informed by community feedback gathered during a comprehensive programming study carried out by the BPL in 2020 and 2021. In addition to a new mixeduse building, the proposed project includes an outdoor plaza and shared community amenities

508
02:34:18.960 --> 02:34:34.720
designed for library visitors, residents, and the public. The proposed project will not provide any on-site vehicle parking spaces, but will provide up to 160 bicycle parking spaces. The proponent has held discussions with Historic New England, the owner of the Otis House, and has confirmed that

509
02:34:34.720 --> 02:34:50.800
Historic New England is amendable to the removal of the existed existing surface parking to establish an enhanced public realm between the project site and the Otis House. In April of 2023, the city of Boston mayor's office of housing issued a request for proposals for the

510
02:34:50.800 --> 02:35:08.000
redevelopment of the branch of the BPL located at 151 Cambridge Street. The site consists of approximately 0.51 acres of land bounded to the south by Cambridge Street, to the west and north by property owned by Massachusetts General Hospital, MGH, and utilized as

511
02:35:08.000 --> 02:35:24.560
part of the Charles River Plaza, and by the to the east by property on which the Otis House is located. The objectives of the RFP were developed in close collaboration with other city agencies including the BPL as well as with key community stakeholder groups such as the West End Civic Association, Beacon Hill

512
02:35:24.560 --> 02:35:40.000
Civic Association, Historic New England and others. Mo received eight proposals for the redevelopment and in December of 2023, the public facilities commission in close coordination with BPL and Mo approved the developer designation of POA and Cass Capital to lead the

513
02:35:40.000 --> 02:35:57.200
redevelopment effort. The letter of intent to begin the article 80 process was submitted in August of 2024. Subsequently, the project notification form was filed on January 8 of 2025. A public meeting was held on February 12th of 2025, which was circulated to the planning department's West End listerve

514
02:35:57.200 --> 02:36:11.920
and published in local newspapers as well as neighboring groups in Beacon Hill in the West End that were part of the initial community planning process. The meeting was well attended and was followed by two subsequent in-person meetings outside of the Article 80 process. on November 12th of 2025 and

515
02:36:11.920 --> 02:36:29.680
March 19th of 2026. PO and Cass have laid out how different types of vehicles will be able to access the site in this plan. The proposal is based on investigation and analysis by the proponent team as well as detailed ongoing input from city staff and BPL planning, housing, transportation,

516
02:36:29.680 --> 02:36:45.200
disabilities commission, public facilities, and city operations. Safety is the number one priority for the vehicle access plan, as it is for the sidewalk improvement plan and bike lane plan along Cambridge Street. The proponent team and the city team conducted independent analyses of a few

517
02:36:45.200 --> 02:37:01.680
different options for getting vehicles onto and off of the site, ultimately agreeing that the proposal described above is the safest strategy with the best achievable outcomes given the very tight and complicated site. Trash removal and pickup times will be coordinated with POA and a private trash hauler to ensure timing does not

518
02:37:01.680 --> 02:37:18.560
interfere with heavy traffic times on Cambridge Street. With that, I would like to thank the members of the public, elected officials, and the West End community who have consistently worked within the RFP and article 80 processes over the last two years and helped to shape the project that you are about to see. I'll now turn it over to David

519
02:37:18.560 --> 02:37:34.960
Leonard of the Boston Public Library to say a few words, followed by Ford Delvakio to walk us through the planning context that was considered in reviewing this project. before the development team begins their presentation. Thank you. >> Uh thank you Camille. Um for the record, I'm David Leonard, president of the

520
02:37:34.960 --> 02:37:52.160
Boston Public Library, a position I've now held for 10 years and have been following this particular project and initiative since its beginning and its inception. Um so I just like to um speak in favor of continuing this project. Um it is one of three innovative

521
02:37:52.160 --> 02:38:09.439
opportunities that are currently active uh to deliver not just a modern and suitable uh responsive branch library to the local communities but also to make a substantial contribution to the city of Boston's housing challenges. And so uh

522
02:38:09.439 --> 02:38:26.160
this project once approved will follow on the heels of our Chinatown um initiative. Um also, um as you heard, uh the current branch, uh which is about 9,000 square feet, will more than double in size, uh allowing us to offer the full range of service that every

523
02:38:26.160 --> 02:38:42.479
community in Boston really uh should have access to locally in their neighborhood. uh in particular the larger children's space, the larger teen space, which it doesn't have today and a uh functional community room with seating for up to 125 people uh is is

524
02:38:42.479 --> 02:38:59.600
really taking the space to a modern standard. Um there will also be classroom and conference rooms for uh meetings which are a vital uh library service to our communities today. Um, in response to community interest in exterior space, the branch itself will

525
02:38:59.600 --> 02:39:14.240
also have its own dedicated reading garden, um, access through the branch that will allow patrons to access the exterior of the, um, of the space as well, um, including access to some green space slightly back from the bustle of

526
02:39:14.240 --> 02:39:29.840
Cambridge Street. So, um, of the number of projects that we, uh, initiated in with our city colleagues, uh, this one had the strongest endorsement very early on from the local community about the viability of this project on this site.

527
02:39:29.840 --> 02:39:45.840
And, uh, you've heard, uh, in the initial introductory presentation um, the amount of feedback that has been garnered through the process. And so, uh, we are excited to see this move forward. And while the timing is still um under review, uh the city of Boston

528
02:39:45.840 --> 02:40:04.399
is committing capital dollars to ensure that the project um will complete itself uh when once the timeline is approved. Um thank you for your time today. >> Thank you. >> Thank you for that. Uh good evening, Vice Chair Shepard, uh Secretary Pimus, members of the board, and director Shen.

529
02:40:04.399 --> 02:40:20.240
My name is Ford Delveio, and I'm the planner reviewer assigned for this project. Uh this is the correct slide, so thank you. In February 2018, the mayor's office of housing launched the housing with public assets initiative to identify municipal facilities that could double as sites for new housing. The West End library emerged as a premier

530
02:40:20.240 --> 02:40:35.840
candidate for this mixeduse approach, offering a unique opportunity to preserve essential library services while integrating residential units. Located on opp site at 151 Cambridge Street, the project sits within the Cambridge Street north side protection area in a

531
02:40:35.840 --> 02:40:50.960
restricted parking overlay district. Proposed library and residential uses are permitted under current zoning. While the building's design is while the building's design is contextually scaled, it would exceed current zoning maximum dimensions. Beyond the building's uses, the project introduces a significant neighborhood benefit. A

532
02:40:50.960 --> 02:41:07.280
new outdoor plaza situated between the development and the historic Otis House. Although the zoning district does not mandate public open space, this plaza will replace a gated surface parking lot and serve as a vital amenity, increasing the library's visibility and strengthening the physical connection physical connection to nearby cultural

533
02:41:07.280 --> 02:41:24.080
landmarks. Taking a wider lens by introduc by in reintroducing residential use with an active ground floor. The project represents a thoughtful evolution of the site once again establishing a contextual urban mixeduse condition in this part of the West End. Thank you. And I will now turn over over to the development team to present in

534
02:41:24.080 --> 02:41:40.800
more detail. >> Chair, could we take uh Rep. Representative Livingstone out of order? >> Yes, let's do that. >> Representative Living Stone, are you on?

535
02:41:40.800 --> 02:41:56.800
>> Yes. Uh thank you and uh thank you for taking me out of order. Um to the chair and and to the members of the committee. Um, I'm here to testify in favor of this project. Uh, I I remember when, uh, John Ahat, Suzanne

536
02:41:56.800 --> 02:42:12.000
Besser, and Karen Corteller years ago told me the city should be doing something like this, identifying this site that led to the city program that's now led to uh, us being here today. Um, this project delivers solely needed uh,

537
02:42:12.000 --> 02:42:28.399
housing and affordable housing in the Binell West End neighborhood area. it um will deliver a much better library than currently exists there which will be a great uh community benefit. Um and there's been a robust process where this

538
02:42:28.399 --> 02:42:44.080
uh project's been shaped uh from the RF through the RFP process to picking um uh POA as one of I think seven people that seven organizations that applied for this to then shaping POA's um project.

539
02:42:44.080 --> 02:43:01.760
the the only complaint I've heard from the community um to the to the latest has been uh about deliveries. I as I've looked at the project and I've thought about it and talked to communities, I think POA has come up with the best solution um for that where there's a

540
02:43:01.760 --> 02:43:20.160
hidden essentially drop off um in front of the building uh that will be used by the library truck and then also um I would imagine will be delivery trucks will find that and then they've promised that uh trash deliveries which will have

541
02:43:20.160 --> 02:43:35.439
to happen on Cameron Street which is incredibly really busy uh will only happen in the morning before rush hour and um so with that I I hope you approve it. I really appreciate you taking me out of order. Thank you. >> Thank you representative. Uh we'll take

542
02:43:35.439 --> 02:43:51.520
one more elected official. Uh that'll be council roof Z. Rufz if you're available. >> She's not on right now so we'll have to come back to her. >> Okay. >> Thank you rep. Livingstone and good evening everyone. My name is Mel Miller. I'm a project manager at preservation of

543
02:43:51.520 --> 02:44:07.840
affordable housing or POA. I'm joined by my colleague Mina Jacob and Amanda O along with our development partner Patrick Kimble of Cass Capital. We have members of our design team and our council in the room and online. And sorry, I just want to say thank you to the secretary. Thank you vice chair and also to director Chen and members of the

544
02:44:07.840 --> 02:44:24.399
board. So, as we've heard by now, right, we all know the site is occupied by the existing West End branch of the Boston Public Library. It is a one-story building that is functionally outdated and underutilized given the site configuration and limited uses. At the

545
02:44:24.399 --> 02:44:39.760
same time, the site is very well located. It's just a/4 mile from where we are currently. It is sitting along Cambridge Street in a dense transitrich area directly adjacent to the historic um Otus House. Next slide, please.

546
02:44:39.760 --> 02:44:55.439
So, the project includes 119 income h uh incomerestricted housing units and approximately 19,000 square feet for the new West End Library branch. In total, the building will contain approximately 176,000 square ft, rising to 14 stories

547
02:44:55.439 --> 02:45:13.120
and approximately 165 ft in height. The project has a floor area ratio of approximately 8, really reflecting the efficient use of this transitoriented, centrallylo site. Next slide, please. So, the 119 affordable apartment homes

548
02:45:13.120 --> 02:45:29.040
are distributed across 12 stories of housing over the twotory library space. The unit mix, which you can see in the top right here, is providing a variety of housing options ranging from the mix of studios up to three-bedroom apartments, all of which will be

549
02:45:29.040 --> 02:45:45.760
affordable to households making below 80% of area median income. And before we move on to more renderings and looking at various angles of the development, I just want to highlight here up front the design strategy. Um, so as we can see right, the massing is really broken up and that's done so intentionally based

550
02:45:45.760 --> 02:46:02.479
on both the neighborhood context and also the uses themselves with the library at the base and its connection to the public realm being expressed um with on those first two floors and then of course the residential component above it. Next slide please.

551
02:46:02.479 --> 02:46:19.279
So I think as we as has been established right this is a very constrained site and just to kind of orient us right we see its relationship here to Cambridge Street running alongside the right of the screen along with the Otis house just at the top right here. The layout does reflect extensive coordination with

552
02:46:19.279 --> 02:46:35.359
the city and design team in order to maintain clear circulation support library operations and integrate the new outdoor civic plaza. Um that plaza itself really is a key organizing feature of the site, creating this welcoming and visible connection between

553
02:46:35.359 --> 02:46:52.399
Cambridge Street, um the library, nearby Otis House, and the broader community, recognizing that this is a neighborhood with very limited open space. In coordination with city with the city, the site plan also features an extended sidewalk along Cambridge Street, which was really done in an effort to enhance

554
02:46:52.399 --> 02:47:08.880
the public realm and improve pedestrian and cyclist safety. If we look at the building for a moment, um you'll see this better more detailed um on the next slide, but access points are carefully located to separate the library and residential functions. Um specifically, we see the entrance to the library sort

555
02:47:08.880 --> 02:47:24.560
of in the center right of the screen. The residential component is coming just off of the pedestrian plaza, which lies in between the building and Otis House. And then you also see the double doors on the bottom right, which are leading to that private library garden that David had mentioned earlier. While we're

556
02:47:24.560 --> 02:47:39.439
on this slide, I'll also just highlight the landscaping plan, which consolidates planting areas and introduces new trees while also providing 28 short-term bicycle parking spaces and convenient locations across the site. So, if we look at the next slide, we see how this

557
02:47:39.439 --> 02:47:55.680
site plan starts to come to life. Um, sorry, next slide, please. Um, so we see how the site plan starts to come to life when we look at the preliminary site logistics plan. We've heard a bit about this already, right? But I think high level just want to note upfront right it it reflects close

558
02:47:55.680 --> 02:48:12.000
coordination with the city with a focus on minimizing conflicts improving safety and maintaining a high quality pedestrian environment along Cambridge Street. As a result the design intentionally consolidates most loading and servicing along Cambridge Street allowing the plaza to remain primar

559
02:48:12.000 --> 02:48:29.359
primarily pedestrian focused. So, we see this green arrow going through the pedestrian plaza. Um, and and what that is indicating is for service um it's I think it says service access way for the transformer access only. That is the only vehicle we anticipate to be within the pedestrian plaza. It would access

560
02:48:29.359 --> 02:48:44.560
the transformer at most for a schedule two times per year. Um, and then of course if emergencies happen. Beyond that, we see the library van situated sort of at the base of the entrance to the plaza off of Cambridge Street. This is its designated space that's

561
02:48:44.560 --> 02:48:59.760
anticipated to be used for short-term daily deliveries along with operational needs as needed. And so the last thing I'll touch on, which we've heard a bit about already, is how residential operations are anticipated to go, which is again to use Cambridge Street. I'll

562
02:48:59.760 --> 02:49:16.479
focus on both trash and then move in and move outs. Trash specifically, we anticipate that happening um four times per week again with working with haulers who can um operate during as during non- peak hours for traffic. So again,

563
02:49:16.479 --> 02:49:33.520
selecting a hauler that can work that can do pickups before 7 a.m. ideally before 6:00 a.m. and then move in and and I'll say sorry trash will be brought to the curb. You see dumpsters sort of in the center bottom of the screen. That's where they will be h housed until trash is picked up and then brought back into the building's internal trash room.

564
02:49:33.520 --> 02:49:49.200
Move in, move outs, again will be managed from Cambridge Street through scheduled windows during non- peak hours to minimize disruption. You know, we talk about 119 units. The biggest activity will happen during the building's lease up, which we anticipate to be over a five-month period. 119

565
02:49:49.200 --> 02:50:05.279
units. That comes out to a few dozen units um each month, a few units each week. And so making sure that those are strategically and well scheduled and managed um during again non- peak hours to minimize disruption. So on the next slide, we can begin to

566
02:50:05.279 --> 02:50:22.479
take a look at a few of the elevations. So here we see the north on the left which is the building's backside um and the south elevation which is the building fronting Cambridge Street which really reflect the project's massing strategy and contextsensitive design that I had noted earlier. The elevation

567
02:50:22.479 --> 02:50:40.080
step and articulate the facade to reduce perceived height introduce vis visual interest and respond to neighboring buildings. The housing above and the library below are clearly expressed while also remaining this cohesive single um building. On the next slide um

568
02:50:40.080 --> 02:50:55.920
we see the west elevation which to orient us now we see the library is on the bottom right and so we're looking at the side of the library. This would also be the side where the li uh where the reading garden would be. And we further see here right how the building engages with its surroundings and addresses

569
02:50:55.920 --> 02:51:12.800
scale along Cambridge Street. And then lastly, if we look at the next slide, um the east elevation, right, we're continuing the same design language with careful attention to setbacks and building articulation. And so what we see here is um the residential entrance at the forefront, the library at the

570
02:51:12.800 --> 02:51:28.000
background with the library's um edge meeting the building's edge. And so I'll just end by looking by by discussing a few of the project renderings um really to get a better sense of the completed building in public realm. So you see the library on

571
02:51:28.000 --> 02:51:44.640
the left along Cambridge Street. Sorry, the whole building on the left along Cambridge Street. And then in the bottom right, we get a better understanding of the library coming alive along with the uh pedestrian plaza on the top right. And then just lastly on the next slide,

572
02:51:44.640 --> 02:52:01.680
we see a few additional views of the building and plaza along with a nighttime rendering in the top right that helps illustrate lighting and visibility at the plaza um in the evening as well. So with that, um, we can go to the next slide and just want to say thank you to the city for its

573
02:52:01.680 --> 02:52:18.240
continued partnership and we look forward to the ongoing coordination. >> Thank you. >> Thank you. >> All right, this is a public hearing and we are now taking public testimony. If you would like to testify in person, please step up to the podium and announce your name, affiliation, and

574
02:52:18.240 --> 02:52:34.960
your position and your position on the proposed project when you are called to speak. If you are on Zoom and would like to testify, please raise your virtual hand. >> I'm sorry. Uh, Councelor Luen is online, so I'd like to just take her before we

575
02:52:34.960 --> 02:52:52.720
start public testimony. >> Councelor, >> hello. Can everyone hear me? >> Yes. >> Yes. >> Hi everyone. Um, Ruth Lian at large city council here. Sorry, I was on here earlier and just couldn't get to unmute on time, but I just wanted to come and

576
02:52:52.720 --> 02:53:09.520
uh voice my support for this project. I want to thank all of the members. I think Rep Living Stone did it really well, shutting out so many like John and so many others who were so involved in making this happen, answering two issues at the same time, making sure that we are preserving and working on our libraries as public goods and helping

577
02:53:09.520 --> 02:53:25.439
with our affordable housing issues. Um, and so I want to express my support. I want to thank all of the residents who have had input, all of the folks who have come together to bring us to where we are now. I do know that there are some outstanding issues around curb cuts and deliveries as discussed, but I also know that we uh have what it takes to

578
02:53:25.439 --> 02:53:43.600
work on those issues as this project move forward. So, thank you for uh for taking me and just want to again voice my support for this project. >> Thank you, councelor. >> Thank you so much um Mr. chair, members of the board, um, including some former colleagues of mine. Um, I'm Kenzie Bach.

579
02:53:43.600 --> 02:53:59.920
I have the honor of leading the Boston Housing Authority, um, and formerly had the honor of being the city councelor in this district, District 8. Um, and, uh, this is my local library, the West End Library Branch. Um, so I just wanted to come uh with all of those hats on to just say how excited I am that this

580
02:53:59.920 --> 02:54:14.800
project has reached this point and express my fullthroated support um both in my personal capacity and on behalf of the BHA which is very excited about the fact that a portion of the units um in this building will house very low-income families that we house all over the city

581
02:54:14.800 --> 02:54:30.560
and in a part of the city where we don't have very much housing um that supports those families um but a part of the city that has a very deep history of housing families. We know that the West End before it was cleared um was a vibrant immigrant neighborhood full of families

582
02:54:30.560 --> 02:54:45.600
including a large number of low-income families. Um and I was looking uh David Leard who's here his uh institution has a wonderful tool called Atlas Scope where you can look at any part of the city and see what was on it in various years. Um and before this site was

583
02:54:45.600 --> 02:55:01.439
cleared, it had 10 family dwellings on just this parcel where we have the West End Library now. Um, so I think, you know, the idea that we would come full circle and manage to put housing for families and for seniors back on this site, um, but do it at the same time

584
02:55:01.439 --> 02:55:16.880
with this state-of-the-art library, um, is just a really exciting thing for the neighborhood. Um, and, uh, you know, from my perspective, when the when the West End was cleared, we did have a whole lot of low-income people who moved out and were never able to move back, and the initial development was very

585
02:55:16.880 --> 02:55:33.439
much all um, market housing. But then in the decades since both the Beacon Hill and West End neighborhood really supported getting more affordable housing in the West End and so there's a number of signature projects from Blackstone Apartments to West End Place to on the Beacon Hill side using former

586
02:55:33.439 --> 02:55:48.640
city schools um like the Peter Faniel school um 250 Cambridge as sites for um affordable housing. But even all of that work um which I'm somewhat proud of by extension because my grandfather was a big part of it at this point happened

587
02:55:48.640 --> 02:56:04.800
you know 40 50 years ago and it's been a long time since we had an opportunity um to house more families at the site. Uh in that period we've seen a steady loss of families especially with children um from both the west end and Beacon Hill. Um, and it's something that I know, um,

588
02:56:04.800 --> 02:56:21.120
from when I was a counselor is a really important priority to the neighborhood to make sure we have families of all incomes. And that's the great thing. This is a mixed income building um, who are able to come and live here and benefit from the incredible services that the library, which is very treasured by the neighborhood, provides. So, um, I want to, they've been lifted

589
02:56:21.120 --> 02:56:36.160
up a couple of times, but want to lift up again, uh, John Ashatz and Suzanne Besser and Karen C Taylor, um, who really were the only people who wrote a sort of Microsoft Word response to the city's, um, public assets ask, though, everyone else was a developer, but these were neighborhood leaders saying, "Yes,

590
02:56:36.160 --> 02:56:52.359
we'd like to see this here." Um, and, uh, there's just been many, many hands since that point, but um, we're just very excited to see it reach this point. So, I want to thank everybody who's been part of it and and put in a strong voice of support for the project tonight. Thank you. Thank you.

591
02:56:54.319 --> 02:57:11.760
>> Hello. I've never done this before, so just bear with me. My name is Steve Zademan and I live at the Blackstone and a tremendous place, a wonderful place to live. I grew up in the old west

592
02:57:11.760 --> 02:57:29.439
end of Boston and lived there until it met its demise in 1955. And thanks to the Boston Redevelopment Authority who kept lists of every single person who was displaced from the West End. At 8 years old, my name was on that

593
02:57:29.439 --> 02:57:45.840
list. That's how I'm living at the Blackstone right now. Tremendous community, wonderful place to live. The staff at the Blackstone is tops. You can't beat it. I've seen five directors since I've been there and currently it

594
02:57:45.840 --> 02:58:02.000
it's the best that it's ever been. But what's unique about that is that like the old West End, it was a melting pot. It is a melting pot. We have certainly black, white, Hispanic, Asian people living in the building, 145 units in

595
02:58:02.000 --> 02:58:17.840
there. Everybody gets along. How is that possible? But you know it's true and it's and I think it is due to the staff that we have there and poa I I know some of you

596
02:58:17.840 --> 02:58:33.920
yes we've never met before by the way so I was hoping somebody would be here for poa but um you do a great job. It's a it's a great place to live and the thought of having another POA property which I followed the whole progress of

597
02:58:33.920 --> 02:58:50.399
this and I was hoping and I was so happy that POA was uh awarded this development contract. Um it it it's a wonderful thing and with the library remember the old library which used to

598
02:58:50.399 --> 02:59:06.880
be at the corner of Line Street at uh and Cambridge Street and my aunt and uncle owned a brooming house up on Line Street where that research building is right now. So I spent a lot of time in that neighborhood growing up and I just for whatever it's worth I grew up

599
02:59:06.880 --> 02:59:23.279
around the corner at the corner of Brighton Street and Allen Street and I once met Leonard Nemoy Drew sitting on the steps of St. Joseph's Church and why is he sitting here? His son was across the street. I

600
02:59:23.279 --> 02:59:38.240
didn't notice that they were filming that documentary for Channel 2. So I started to talk to him and when I told him I was from the old West End, his eyes just lit up and we started playing the Jewish geography,

601
02:59:38.240 --> 02:59:54.080
you know, did you know this one? Did you know that one? And it turned to the Winshell school. Who was your first grade teacher? Well, I think everybody in the West End had Miss McGovern. And it so it seems Kenzie might know, might

602
02:59:54.080 --> 03:00:10.160
have heard those those stories. Um, but I I just wanted to speak in favor of this project and and I thank everybody. Thank you all for for what you do. I've never I I've never been aware of that, but it's a great thing

603
03:00:10.160 --> 03:00:31.680
and I think I think it's going to be a great thing for the city as well. So, thank you all. >> Thank you. Uh, thank you, Vice Chair Shepard, members of the board, Madam Secretary, Director Shed. My name is Mark Delasio. I am a business representative for the Carpenters Union, Local 327 in Boston.

604
03:00:31.680 --> 03:00:48.160
And, uh, we just want to be on the record as being in full support of this project. Uh, looking forward to it. It looks like a a beautiful project and it's going to be a great addition to the neighborhood. Thank you. >> Good evening, members of the board. Thank you for the opportunity to speak. My name is Daniel Daly. I'm a lifelong

605
03:00:48.160 --> 03:01:04.319
Boston resident and I'm also a business representative for Local 103 with the electricians and uh Boston needs housing. Boston needs jobs and we certainly need libraries. So, I'm in full support of this project. That's wonderful. And I love the story back there. My brother-in-law is a West Ener. I get to talk to him. So, thank you very

606
03:01:04.319 --> 03:01:25.359
much. Appreciate it. >> Colin Zik, you can unmute yourself. All right. Uh, can you hear me? >> Yes, I can. >> All right. Very good. Um, I not sure why the video is not on, but I'm going to proceed anyway. So, I'm Colin Zik. I'm

607
03:01:25.359 --> 03:01:41.600
the current president of the Beacon Hill Civic Association. As several of the speakers have said, the idea for this project came from leaders of the Beacon Hill Civic Association. And as an association, we are strongly in support of the project. Uh we appreciated the

608
03:01:41.600 --> 03:01:59.040
collaborative nature of the RFP process. Uh and we look forward to refining the project consistent with the public comments that we have made. Uh as was alluded to by some of the other commenters, we do have concerns about some elements of the design. Despite our

609
03:01:59.040 --> 03:02:14.479
full throtted fullthroated support of the project, uh we are concerned that there are uh seating elements of the design that will lead to negative uses. As someone who has lived in this neighborhive

610
03:02:14.479 --> 03:02:30.960
use of illegal drugs in and around this area, including this week reporting active drug use under the Appleton foot bridge. This is a concern that we don't want to have travel up Cambridge Street. Uh and we think the seating area needs to be adjusted accordingly. As was also

611
03:02:30.960 --> 03:02:48.160
alluded to, we have concerns about the traffic and parking element of this. Um if you look at another affordable housing location on Cambridge Street, 250 Cambridge, there's a significant problem with a driveway there being blocked by food delivery drivers. We

612
03:02:48.160 --> 03:03:03.279
think this needs to be accounted for. We also think that the timing of the pickups and drop offs and so forth that need to happen are probably not best addressed at 6:00 to 7:00 in the morning when shifts change at Mass General

613
03:03:03.279 --> 03:03:20.880
Hospital. That issue will only be exacerbated by the completion of the two new Mass General buildings and we think that needs to be addressed. Uh we hope that these will be addressed as we go forward. And finally, the one thing uh we noted Mr. Leon Leonard from the uh

614
03:03:20.880 --> 03:03:37.760
BPL. This project is going to take about 2 and 1 half to 3 years and put the library out of service. There is no current plan to put a replacement library or significant library services in place of the missing library. We think that needs to be addressed. But

615
03:03:37.760 --> 03:03:54.399
again, we support the project and we look forward to refining these issues. Thank you. >> Thank you, Elena Ushukova. You've had your hand up and down. I'm not sure if you were trying. Go ahead, Elena.

616
03:03:54.399 --> 03:04:10.240
You need to unmute yourself. >> Hi. Uh my name is Alina and I'm very thankful for your presentation, but I'm going to give my arguments uh in opposition to this project. I'm living

617
03:04:10.240 --> 03:04:27.840
two uh two buildings away from the project which is planning to be there. So I know this area very well. I'm actually here from every single day from morning till night and I do know this

618
03:04:27.840 --> 03:04:43.040
location very well. So in the pictures it was seen that the new project is going to be between AI uh AI's house and MGH. That's correct. But um it's very

619
03:04:43.040 --> 03:04:59.520
dense location and the space between the project and MGH is just tiny. It just building to building. So my first argument against or in opposition of

620
03:04:59.520 --> 03:05:18.560
this project is uh density very little space very small location and very close to the ais house plus next to the ais house there is another there is a there is a church so this is

621
03:05:18.560 --> 03:05:35.840
actually a historical area and the new building it's going to be residential building. Well, I don't think it's appropriate right here. Speaking about the library, you mentioned it's going to be a mixeduse approach, but uh uh I'm

622
03:05:35.840 --> 03:05:50.479
the member of the library. I'm very much uh satisfied with this library and the most the strongest uh argument is infrastructure uh around that. The roads are very very

623
03:05:50.479 --> 03:06:10.080
bad around. So the traffic is terrible and actually you know there is only one grocery store in this area. It's just Whole Foods Market, nothing else. >> Are you finished?

624
03:06:10.080 --> 03:06:27.279
>> Elena? >> No, actually almost finished. I have a question. Um what was um uh the goal? What was the argument to choose this specific location? Because I don't

625
03:06:27.279 --> 03:06:41.920
understand why the library which we have right now is not a good building. I mean it's pretty good. So why this particular location was chosen for the new project?

626
03:06:41.920 --> 03:06:56.880
Um, so the the proponent doesn't respond directly to questions, but the board members will take your question under consideration or may ask the city developer. All right, you've passed your time. Is was there any concluding

627
03:06:56.880 --> 03:07:14.479
remarks you wanted to share? >> Uh, yes. So, one more thing. Uh, shadow and line. You mentioned that new trees will be grown over there. But uh I know I mean I can see a lot of new trees are

628
03:07:14.479 --> 03:07:31.279
being planted here but the old ones um are actually dying because there is not enough sunlight here and a lot of shadow and even uh near the whole foods market which is close to the project which you

629
03:07:31.279 --> 03:07:48.080
are planning. um people usually enjoy uh used to enjoy enjoy sunlight but the new tower of MGH and if this new building will be behind that there won't be light at all not speaking about the sun and

630
03:07:48.080 --> 03:08:06.160
not speaking about the sun for growing trees >> okay thank you very much Elena >> there is nobody there's nobody else line. >> All right. >> Thank you.

631
03:08:06.160 --> 03:08:21.279
Are there any questions or comments from the board? >> Uh yes. Thank you, Mr. Chair. Um I am very very excited to uh vote in support of this project. I remember vividly being with a different mayor. I was in a

632
03:08:21.279 --> 03:08:36.960
different role talking about leveraging um publiclyowned properties to help develop more affordable housing. And and none were more uh uh exciting for us to explore than uh libraries. So, thank you, Mr. President, for your great

633
03:08:36.960 --> 03:08:51.680
leadership. This is an exciting project, not only for the housing that it will bring back to the West End. And sir, I have to tell you, you said this was your first time testifying. That was one of the most compelling testimonies I've ever heard in my time here. So, thank you for being here. But it it's important to note that the historical

634
03:08:51.680 --> 03:09:07.840
aspect 12,000 individuals were displaced from the west end in the name of uh you know urban renewal back in the 1950s and early 60s and um uh we are uh slowly but nevertheless rectifying that

635
03:09:07.840 --> 03:09:24.000
with projects like this. It looks good. It's going to be transformative for the West End branch. I mean, we've seen what other branches, particularly my favorite Jamaica plane branch with with that have seen been untouched for decades and now just given you see more people use them, more young people use them. It's really

636
03:09:24.000 --> 03:09:39.920
really exciting. So, support this unconditionally. Um, I'm nothing if not consistent. I uh the fact that it's going to be 12 or 14 stories, will there be um any um photovoltaics on the roof? I know there's some uh restrictions where we are because I know this

637
03:09:39.920 --> 03:09:55.520
building for example isn't a good candidate but can you talk about that? >> Yeah. So I'll say the building will be designed and built to passive house standards along with meet um lead gold certification. However, my understanding is that just given the footprint of the roof the a PV system was just not able

638
03:09:55.520 --> 03:10:11.840
to the roof wasn't able to support the system. >> No. And and that makes sense. It's very it's it's the way it's narrow that it would need but it's it's good to hear in the passive house standards it would be great as well. So, um, yeah, I'm I'm excited to see this and, uh, thank you all the members of the community and those who've taken the time to weigh in

639
03:10:11.840 --> 03:10:26.560
and been a part of this process. It's a much better project for your advocacy. Thank you. >> Thank you. To me, this is the the best kind of public private partnership, you know, that um we've got an incredibly exciting

640
03:10:26.560 --> 03:10:44.720
reuse of a public asset um that will result not only in a in a new expanded state-of-the-art library, but significant affordable housing and to Kenz's point, um deeply affordable housing, which you know, we we were

641
03:10:44.720 --> 03:11:01.120
we're were successful at a as a city. We see a lot of these projects coming through developing affordable units, but not all of them reach uh to a 30% area median family, which um is something to be really proud of. And so I'm I'm

642
03:11:01.120 --> 03:11:18.720
really excited I to see this. I hope it becomes a model for other public facilities around the city um to create more affordable housing while we uh redevelop those public assets that the city that the city owns and manages. So

643
03:11:18.720 --> 03:11:35.920
kudos to POA, kudos to um Mo, kudos to the community members that have uh worked tirelessly to make this the best project it can be. Obviously, there's still some details to be to be worked on. Uh, but I think this is just a great

644
03:11:35.920 --> 03:11:53.920
a great moment for the project. Thanks. >> And yes, I I would just ask quickly for the team. Um, first of all, thank you for your thoughtful suggestions and plans for the trash removal, but I I would just say if you could please monitor it as we go along and um just

645
03:11:53.920 --> 03:12:10.640
stay um in relationships with the community to make this process as smooth as possible. Thank you. Are there any other questions or comments? Seeing and hearing none, is there a motion on the floor? >> So moved. >> Second. >> There's a second. All in favor?

646
03:12:10.640 --> 03:12:38.240
>> Any oppose? eyes have it. Thank you. >> You're welcome. >> 25 >> 24 >> 24 >> I'm ready for wishful thinking. >> All right, we can go. Item number 24

647
03:12:38.240 --> 03:12:53.439
requests authorization to one issue a scoping determination waving further review pursuant to section 8A-2 and section 80B-5.4D 4 D of the zoning code for the proposed

648
03:12:53.439 --> 03:13:09.359
50 Congress Street project and two issue certification of completion for the proposed project pursuant to section 80B-6 of the zoning code upon successful completion of the article 80B large

649
03:13:09.359 --> 03:13:25.840
project review process and three accept quiet claim deed for the certain temporary and limited property interest in the proposed projects project site and four enter into a

650
03:13:25.840 --> 03:13:41.920
contract for payment in lie of taxes among the city of Boston, the BRA and the proponent in connection with the proposed project and to take all related actions included without limitations executing the delivery a cooperation

651
03:13:41.920 --> 03:13:57.920
agreement and transportation access plan agreement. Dylan. >> Good evening, Vice Chair Shepard, members of the board, Director Shannon, Secretary Paul Hemis. My name is Dylan Norris. I'm a project manager in the development review division of the planning department. I am here today to present an applicant of Marowoo's

652
03:13:57.920 --> 03:14:13.279
downtown to office to residential conversion program, the proposed article 80B large project located at 50 Congress Street in the downtown neighborhood of Boston, as well as the proposed 121B agreement in order to effectuate the downtown residential conversion incentive pilot program. You can go to

653
03:14:13.279 --> 03:14:28.800
the next slide. On December 17th, 2026, 50 Congress Street LLC, the proponent, applied to Mayor Woo and the BPDA's downtown residential conversion incentive pilot program. The pilot was authorized by this board on October 12th, 2023. Based

654
03:14:28.800 --> 03:14:44.960
on BPDA staff review under article 80 and review under the pilot program, this proponent has been selected to receive a pilot agreement based on the pilot program criteria. The proponent will upon approval by the BPDA board enter into a pilot agreement among the city of Boston and the BPDA. In order to comply

655
03:14:44.960 --> 03:15:00.800
with the rules and regulations under Massachusetts General Law Chapter 121B section 16, the BPDA must take a property interest in the site which refers to the quick claim deed that you mentioned earlier. On January 2020 uh 26th, 2026, the proponent filed a letter

656
03:15:00.800 --> 03:15:16.000
of intent with the planning department. Based on the uh letter of intent submitted, the planning department staff recommended that the director issue a letter of waiver for the formation of an impact advisory group. The proposed project does not include any major external construction as it is adaptive

657
03:15:16.000 --> 03:15:31.279
reuse of the current underutilized commercial space. It is an applicant of the pilot program and complies with the requirements of the executive order and thus the IG formation uh should be waved. A project notification form was filed with the BPDA on February 27th,

658
03:15:31.279 --> 03:15:48.399
2026, submission of which initiated the large project review. The BPDA hosted a virtual public meeting on March 24th, 2026, which was well attended and wellreceived. The public meeting was noticed on the BPDA's events calendars and sent to the downtown neighborhood distribution list. The comment period on

659
03:15:48.399 --> 03:16:05.200
the project notification form ended on March 30th, 2026. You can go to the next slide. The project site located at 50 Congress Street uh consists of an approximately 20,000 square foot parcel bounded by Exchange Place to the north, Kilby Street to the east, and Haw Street to

660
03:16:05.200 --> 03:16:23.520
the south, as well as Congress Street to the west within the Boston's financial district uh downtown Boston and the financial district area. The project site is currently occupied by an existing 10-story office building with a gross floor area of approximately 181,000 square ft. Next slide.

661
03:16:23.520 --> 03:16:39.920
The proposed project will convert the existing 10-story building into approximately 169 residential apartment units, including 135 market rate and 34 incomerestricted units spread over nine studios, 16 one-bedrooms, and nine two-bedroom apartments to be offered in

662
03:16:39.920 --> 03:16:54.720
qualified applicants earning no more than an average of 60% of the area median income. The proposed project will also include approximately 7,300 ft² of groundf flooror commercial amenity space uh commercial retail space and potentially consisting of a similar

663
03:16:54.720 --> 03:17:11.200
restaurant and neighborhooding uh neighborhood serving uses. Uh thank you and that concludes the presentation. The proponent team is available to answer any questions that the board have uh related to the project. Thank you. >> Are there any questions or comments from the board?

664
03:17:11.200 --> 03:17:27.439
Uh again, love to see um office conversions being done. I think there somewhere around 25 applications in the city of Boston. Um you know, historical sites and people have the opportunity to become residents in the neighborhoods of

665
03:17:27.439 --> 03:17:43.120
the city of Boston. All I would ask again is that during the construction process, uh we use you know qualified and you know general contractors and subcontractors that follow um you know apprentichip languages and things of that nature so that young men and women in the city of Boston can have the

666
03:17:43.120 --> 03:17:58.160
opportunity to be a part of the growth of the downtown Boston area. Uh seeing and hearing no other questions or comments with the pleasure of the board. >> Is there a motion on the floor? >> So moved. >> Second. >> There's a second. All in favor? I >> I

667
03:17:58.160 --> 03:18:16.319
>> Any oppose? Eyes have it. Thank you. >> Thank you. Item number 25, request authorization one, issue certification of approval for the proposed development located at One

668
03:18:16.319 --> 03:18:33.040
State Street pursuant of article 80, small project review of the zoning code. Two, enter into a pilot agreement for the proposed project. And number three, accept a quit claim deed for a certain temporary and limited property interest

669
03:18:33.040 --> 03:18:49.760
in the proposed project projects project site. And four, enter into a contract for payment in lie of taxes among the city of Boston and the BRAA and the proponent in the connection with the proposed project and to take all related actions. Jack.

670
03:18:49.760 --> 03:19:06.479
>> Good evening, Vice Chair Shepard, members of the board, Director Shen, and Secretary Pimis. Uh my name is Jack Gilman and I'm a project assistant with the development review team. Uh I'm here before you tonight to present an applicant of Mayor Woo's downtown office to residential conversion program, the

671
03:19:06.479 --> 03:19:22.000
proposed article 80 small project located at one state street in the downtown neighborhood of Boston, and the proposed 121B agreement to effectuate the downtown residential conversion incentive pilot program. Next slide.

672
03:19:22.000 --> 03:19:38.479
November 10th, 2025, State House LLC applied to the mayor applied to Mayor Woos in the BPTA's downtown residential conversion incentive pilot program authorized by the BPTA board on October 12th, 2023. Based on BPTA staff review under article

673
03:19:38.479 --> 03:19:53.920
8 and review under the pilot program, the proponent has been selected to receive a pilot agreement based on the pilot program criteria. The proponent will upon approval by the BPDA board enter into a pilot agreement among the city of Boston and the BBTA.

674
03:19:53.920 --> 03:20:11.120
In order to comply with the rules and regulations under Massachusetts General Law Chapter 121B section 16, the BPTA must take a property interest in the project site. A small project review application was filed with the BPDA on March 26, 2026,

675
03:20:11.120 --> 03:20:26.239
submission of which initiated the small project review. The BBTA hosted a virtual public meeting on April 15, 2026, which was well attended and wellreceived. The public meeting was noticed on the BBTA's events calendar and sent to the downtown neighborhood

676
03:20:26.239 --> 03:20:41.520
distribution list. The comment period ended on April 27th, 2026. Next slide. The project site includes approximately 4,632 square feet of land located at one State

677
03:20:41.520 --> 03:20:56.319
Street in the downtown neighborhood at the intersection of Washington Street and State Street. The existing site includes approximately a 64,428 ft commercial office building with existing retail uses on the ground floor.

678
03:20:56.319 --> 03:21:13.279
Next slide. The proposed project looks to renovate and convert the long-existing building at the site by changing its legal use from commercial office to residential multifamily housing on floors 2 through 14 with a 3,630

679
03:21:13.279 --> 03:21:28.800
square foot uh ground flooror retail on Washington Street remaining on the first floor. The proposed project will create up to 76 residential dwelling units in approximately 46,999 square feet of gross floor area and

680
03:21:28.800 --> 03:21:44.720
include uh ample on-site bicycle storage containing 52 bicycle parking stations. The unit mix will be comprised of 27 studio apartments and 49 one-bedroom apartments. The proposed project will preserve the existing building envelope,

681
03:21:44.720 --> 03:22:01.200
structural system, and primary facade openings. The pro proposed project scope is limited to interior work within the building at the site with no expansion to its existing footprint or facade. That thank you and that concludes the presentation. The proponent team is available to answer any questions the

682
03:22:01.200 --> 03:22:16.720
board may have related to the project. >> Thank you. Are there any questions or comments from the board? >> Seeing and hearing none. Is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. Thank you.

683
03:22:16.720 --> 03:22:41.520
Nice job, Jack, on your first presentation. >> Well done. >> All right, nice job. Item number 26, request authorization to one, issue a scop and determination waving further review pursuant to section 8A-2

684
03:22:41.520 --> 03:23:00.720
and section 80B-5.3D of the zoning code for the 320 Summer Street project. And number two, issue certification of completion for the proposed project pursuant to section 80B-6 of the code upon successful completion

685
03:23:00.720 --> 03:23:16.880
of the article 80B large project review process. And three, authorize the director to take any and all actions and execute any and all documents including without limitation executing and delivering a cooperation agreement,

686
03:23:16.880 --> 03:23:31.120
transportation access plan agreement, and any and all other documents and agreements the director deems appropriate and necessary in connection with the proposed project. And four, authorize

687
03:23:31.120 --> 03:23:48.319
the director to accept a what is this? Quit plan. Uh quick claim. I I need help with that one. >> Quick claim. >> Yeah, quick claim. Sorry about that. Tongue twister for me. Deed for certain temporary and limited property interest in the proposed projects project site.

688
03:23:48.319 --> 03:24:05.279
And five, authorize the director to enter into a contract for payment in lie of taxes among the city of Boston and well city of Boston. in the Boston Redevelopment Authority and the HC 320 Summer Street LLC in connection with the

689
03:24:05.279 --> 03:24:20.880
proposed project. Dylan, >> good evening again, Vice Chair uh Shepard, members of the board, Director Shen, and Secretary Paul Hemis. My name is Dylan Norris. I am a project manager with the development review division of the planning department. And not to be duplicative, but I am here to present you an applicant of the Marw's downtown

690
03:24:20.880 --> 03:24:35.760
office to residential conversion program. the proposed article 80B large project located at 320 Summer Street in the South Boston waterfront neighborhood of Boston as well as the proposed 121B agreement in order to effectuate the downtown residential conversion incentive pilot program. You can go to

691
03:24:35.760 --> 03:24:52.160
the next slide. On March 5th, 2026, 320 Summer Street LLC, the proponent applied to Marw and the BPD's downtown residential conversion incentive pilot program authorized by this board on October 12th, 2023. Based on BPDA staff review

692
03:24:52.160 --> 03:25:08.800
under article 80 and review under the pilot program, the proponent has been selected to receive a pilot agreement based on the pilot program criteria. The proponent will upon approval by the BPDA board enter into a pilot agreement with the city of Boston and the BPDA. In order to comply with the rules and regulations under Massachusetts General

693
03:25:08.800 --> 03:25:25.439
Law Chapter 121B section 16, the BPDA must take a property interest in the project site. On April 3rd, 2026, the proponent file filed a letter of intent with the BPDA. Based on the LOI submitted, planning department staff recommended uh that the director issue a

694
03:25:25.439 --> 03:25:41.680
letter of waiver for the formation of the impact advisory group. The proposed project does not include any major external construction as it is an adaptive reuse of a currently underutilized commercial space. It is also an applicant of the pilot program and complies with the requirements of the executive order and thus the IG

695
03:25:41.680 --> 03:25:57.680
requirement was waved. A project notification form was filed with the BPDA on April 7th, 2026, which submission of which initiated the large project review. The BPDA hosted a virtual public meeting on April 29th, 2026, which was well attended and wellreceived. The public meeting was

696
03:25:57.680 --> 03:26:14.000
noticed on the planning department's events calendar as well as sent to the South Boston Waterfront neighborhood distribution list. The comment period for the project notification form filing uh concluded on May 7th, 2026. The the project site uh includes approximately 18,800 square ft of land

697
03:26:14.000 --> 03:26:29.760
located at 320 Summer Street in the Fort Point Channel neighborhood at the intersection of Summer Street and A Street. The existing site uh includes an approximately uh 122,000 ft brick and beam building uh composed of two originally distinct warehouse structures

698
03:26:29.760 --> 03:26:46.000
that were combined by a previous owners of the property. Next slide. The project proposes to renovate and convert and expand interior space within the long-existing combined brick and beam buildings by changing its legal use from commercial uh office to residential

699
03:26:46.000 --> 03:27:03.840
multif family housing with ground uh with an addition of new ground floor retail along a street and the construction of a partial mezzanine level to accommodate loft style residential units. The propo the proposed project will create up to 145 residential dwelling units in approximately 130 uh,000 square ft of

700
03:27:03.840 --> 03:27:19.520
new residential GFA, including ground floor retail of up to 7,000 square ft on a street and approximately uh 2,300 ft of amenity space along uh Summer Street as well as ample on-site bicycle storage. an existing roof deck of

701
03:27:19.520 --> 03:27:34.960
approximately 4,000 square or 400 square feet will be improved with accessibility accommodations for residential units. The Unimix will be comprised of 46 studio apartments, 76 one-bedroom apartments, and 23 two-bedroom apartments. The proposed project will

702
03:27:34.960 --> 03:27:51.279
preserve the existing building envelope, structural systems, primary facade openings, and the the scope of the project is limited to interior work with the combined buildings on the site with no expansion to its existing footprint or facade. Thank you. And that concludes the presentation. The proponent team is available to answer any questions you

703
03:27:51.279 --> 03:28:06.479
may have. Thank you. >> Thank you, Dylan. Are there any questions or comments from the board? >> I would just say I think tonight might be a record for for the number of conversion projects we've seen and it's it's just a it's it's a great initiative.

704
03:28:06.479 --> 03:28:22.399
um 29 affordable units is a great outcome and so um excited to see this specific project but broad more broadly the the number of conversions that we've been processing. Thank you. >> Thank you. >> Thank you

705
03:28:22.399 --> 03:28:38.160
>> to to that point. Thank you um Mr. Chair and thank you for the question uh board member Bennett. Um, are we going to get to a point where the project ceases because we've sort of exhausted the in the potential inventory? >> John, I'm going to have our policy

706
03:28:38.160 --> 03:28:53.520
manager take that one. >> I I don't mean this as a gutch. I certainly don't mean this as I I'm I'm genuinely curious. I I I think that cities across the globe are trying to figure out what to do with downtown

707
03:28:53.520 --> 03:29:09.680
spaces as the sort of everyone in the office 9 to5 isn't what it used to be pre2020. Um some are looking at data centers is sort of making a push there. I think Boston more than any other city is really successfully shephering the residential conversion. So I'm curious

708
03:29:09.680 --> 03:29:26.160
is it >> do we have a number that that sort of the sweet spot and are we getting close to it? Uh so good evening. I'm John While. I'm head of office to residential conversions at the planning department. Uh thank you for the question. Uh I I think that it's we we still have a lot

709
03:29:26.160 --> 03:29:44.080
of very good donor buildings out there and a lot of there still is frankly some challenges in the class B and class C office space as well as cl uh challenges in the life sciences space as well. So I think that we've made meaningful progress. We're at um to your point uh

710
03:29:44.080 --> 03:29:58.560
Vice Chair Shepard, we're at 26 applications to convert 31 buildings. This is 1,785 units of housing being created, including 336 affordable. It's 1.5 million square ft of office, but that is

711
03:29:58.560 --> 03:30:15.680
still approximately, I guess, 18 or 19% of the vacant space out there. So, there still is quite a lot of vacant space in the class B and class C. And I think that there's still I think that there still is a lot of room for a lot of good success to happen in the coming years. I don't think by any means we've exhausted

712
03:30:15.680 --> 03:30:32.000
the the supply of buildings out there. I think that uh it also behooves us to to be creative as we go forward. We've evolved this program since its launch in October of 2023. And I think that we'll look to continue to evolve it to uh meet the realities of the market and see the

713
03:30:32.000 --> 03:30:48.319
opportunities that are before us. So I think there's more to come and a lot of good stuff that's still on the way. That's helpful. And I think you said something that's even more impressive is that if if if we've only looked at about 18% of sort of the potential universe >> to get to 18% in two and a half years is

714
03:30:48.319 --> 03:31:04.239
pretty darn good and it's very challenging uh development market. So >> yeah, I think well done. Thank you. >> Thank you. Thank you for the question too. Uh are there any more comments or questions from the board? Hearing and seeing none. Is there a motion on the floor?

715
03:31:04.239 --> 03:31:28.960
>> So moved. Second. >> All in favor? >> I >> I. >> Any oppose? Eyes have it. Thank you. >> Thank you. >> Thank you. >> Item number. >> Okay. So, okay. Straight to 29.

716
03:31:28.960 --> 03:31:45.120
>> Uh, contractual payments. I need a motion to pay our bills. >> I move that we pay our bills. Second that motion. >> All in favor? >> I >> I >> oppose. Eyes have it. >> Personnel.

717
03:31:45.120 --> 03:32:01.680
>> Good evening. Thank you, vice chair. We have one item for your consideration on the BRA agenda with exact details included in the board memo. We have one status change. In the administration division, Michelle Goldberg will now

718
03:32:01.680 --> 03:32:18.800
serve as chief procurement officer. relieving me of my duties. That's all. >> Thank you. >> Are there any? >> Yeah. Are there any >> Is that a vote? >> Yes. >> Okay. >> Are there any questions or comments from the board?

719
03:32:18.800 --> 03:32:34.160
>> Seeing and hearing none. Is there a motion on the floor? >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. >> Thank you for your service. And next we will turn it over to Director Shen for your remarks.

720
03:32:34.160 --> 03:32:48.720
>> Good evening members of the board. I want to start uh this month's report with just a summary of the development projects that the board approved tonight. Um we approved six new development projects, 611

721
03:32:48.720 --> 03:33:03.760
total new residential units of which 214 of them will be incomerestricted. Um the total investment of these projects when built will uh be approximately amount to about $400

722
03:33:03.760 --> 03:33:20.640
million. Uh these projects will deliver 7 uh 42,000 square ft and when constructed the projects will put approximately 700 trades people to work and create 68 direct jobs and 345

723
03:33:20.640 --> 03:33:37.359
indirect jobs. Uh as noted by members of the board tonight that um the office to residential conversion program is still going strong. Uh four of the six projects to approve will be converting vacant office spaces uh to new homes

724
03:33:37.359 --> 03:33:53.600
from the backbay to the downtown and into the Fort Point neighborhood. Um and it shows the robustness of this program. Uh the pro projects uh will deliver 430 430 new units of housing and since the

725
03:33:53.600 --> 03:34:09.920
launch of the program um we will now be delivering uh 1,7885 units of new housing uh in areas where housing is desperately needed. Um we're looking forward to seeing many of these

726
03:34:09.920 --> 03:34:26.399
units actually come online. Six of these projects are currently under construction. Um uh turning to the zoning um adopted by the board this evening um that this includes new zoning for the Chinatown neighborhood as well

727
03:34:26.399 --> 03:34:43.920
as in the uh citywide uh sign code. The updo updated zoning for Chinatown will remove barriers to uh opening new businesses uh protect the historical historic row houses in the neighborhood and improve climate resiliency in the

728
03:34:43.920 --> 03:35:01.120
neighborhood. This zoning was informed by the feedback uh that staff heard from uh the neighborhood uh and members of the neighborhood over the last couple of years about uh making sure that the zoning um protects the cultural identity of

729
03:35:01.120 --> 03:35:18.720
Chinatown and also to uh support new immigrants and to pro provide affordable housing and local commercial spaces. I want to thank the community for their input actually quite vigorous input um because it took uh over two years of

730
03:35:18.720 --> 03:35:34.319
going back and forth. Um but I believe we achieved a good balance and compromise between the different uh points of view. Um, now as for the new sign code, um, this zoning will, um,

731
03:35:34.319 --> 03:35:51.600
allow small businesses to put up signage much more quickly and, uh, by providing clear regulations and eliminate unnecessary review and wait times. Both of these zoning updates will move now move on to the Boston Zoning Comm

732
03:35:51.600 --> 03:36:09.120
Commission for adoption next month. Um there were also three uh certificate of of completions of which I want to highlight just two. One the the project at 1595 to 1599 Columbus Avenue in Jamaica plane delivered uh a

733
03:36:09.120 --> 03:36:24.479
building with 100% affordable uh units on site. Um this building also achieved passive house um standard um with renewable energy production on site and of course enhance the streetscape and

734
03:36:24.479 --> 03:36:39.920
improve the sidewalks in the vicinity. Another one that actually uh was a project that took a number of years is the the renovation of the Commonwealth Pier which is actually going to be the new headquarters for Fidelity

735
03:36:39.920 --> 03:36:55.760
Investment. Um, of course, many of you know that the Fidelity is bringing back their workers five days a week and in this particular com the completion of this project will facilitate that facility that that return to office. Um

736
03:36:55.760 --> 03:37:12.160
this is of course the old World Trade Center and um and then the project delivered new and upgraded outdoor public space including a new public plaza uh public restrooms and seating areas, new lighting, landscaping and an

737
03:37:12.160 --> 03:37:29.760
extension of a harbor walk around the entire pier. Um, it also provided ADA accessible lobby space and restoration and renovation of the historic head house. Um, it also provides docking space for new water shuttle and there

738
03:37:29.760 --> 03:37:46.720
would be a contribution of $100,000 to uh local nonprofit organizations supporting financial literacy, workforce training, and other harbor related uses. Um, I want to end my report by actually

739
03:37:46.720 --> 03:38:03.279
sharing a a piece of um good news, but um but at the same time um a loss to the department. Uh many of you may already know that on May 4th, Mayor Woo announced the appointment of um of a new

740
03:38:03.279 --> 03:38:18.560
parks commissioner and deputy chief of open space. And the appointment goes to our own deputy chief of urban design, Diana Fernandez Bibbo. Um Diana has been since her arrival at the planning

741
03:38:18.560 --> 03:38:34.880
department a relentless uh advocate for exceptional design and um making sure that the work of the department uh creates places of identity and belonging for all Boston residents. Um she has also been a critical

742
03:38:34.880 --> 03:38:50.720
component of our effort to change the culture and planning and development in Boston. Um she forged an incredibly ambitious agenda. Um she also um recruited a number of really key staff members that have been contributing to

743
03:38:50.720 --> 03:39:06.880
the work that you see every month. Um she also uh advocated advocated for a design vision uh to promote uh predictability in the design review procedures and to ensure uh quality high

744
03:39:06.880 --> 03:39:24.800
quality design. Um also tonight of course you saw Breeze's presentation of the continuation of the color flows um uh tactical urbanism that the department uh created under her leadership. Uh I am incredibly grateful

745
03:39:24.800 --> 03:39:43.120
for her dedication to her team and uh to this department. Um I will I think I represent a general sentiment from the staff that we will miss her here and really appreciate the spirit of creativity. Um and always doing her work

746
03:39:43.120 --> 03:40:00.399
with great energy and always with a smile. Um, we know she's going to be a great asset to the mayor in her new role at the parks and recreation department and as the newly created deputy chief of open space and I think we all look forward with to working with her in her

747
03:40:00.399 --> 03:40:16.720
new role. Um, that ends my report. Thank you. >> Thank you. Congratulations. Uh, with that I need a motion to adjourn the meeting. >> So moved. >> Second. >> All in favor? >> I. >> Any oppose? Eyes have it. Thank you all.

748
03:40:16.720 --> 03:40:21.000
>> Thank you. Thank you. Good job.