00:00:00.320 --> 00:00:21.760
All right, it's uh 6:03. I'm going to start uh the presentation, but before that, um does the council member want to uh representative want to say something or introduce themselves? >> I'm not seeing anybody from the council office, but this is Julie Orba and I am

2
00:00:21.760 --> 00:00:36.960
the communications and public engagement department and the liaison for district 4. So, um, taking notes and be sure to share things with the, um, residents and, yeah, thanks for having the meeting. >> All right. Thank you.

3
00:00:36.960 --> 00:00:54.800
If that's that's all then, uh, we can begin with the presentation. Uh, welcome to the public meeting for city project number 103309. This is for North Tarant Parkway and North Beach Street intersection improvements.

4
00:00:54.800 --> 00:01:10.159
Um my name is Philip Tren and I'm the project city project manager. Uh we have our um design consultants Fzen Nichols. If you can introduce yourselves uh Fahad. Yeah. Hi everyone. Uh my name is Fad Rajabali. I'm with Fzen Nichols and

5
00:01:10.159 --> 00:01:25.520
we're the design consultant on this. And uh with myself I've got Adam Cross as well. We'll be here to answer any questions that you have about this project. >> All right. Um, also we have uh city staff. Um, my pro program manager Chad

6
00:01:25.520 --> 00:01:40.479
Allen is on the line. Go ahead and introduce yourself, Chad. >> Good evening, everyone. My name is Chad Allen. I'm the engineering manager for the mobility team and thank you for joining the meeting tonight. >> Okay. Do we have anyone else from uh the

7
00:01:40.479 --> 00:01:57.600
city of Fort Worth? >> Yeah, this is Randy Horton. I'll be the senior inspector on this project. The inspector is Rodrik Baker, but he's on vacation this week. All right. >> I just doubt it. Apologize for the

8
00:01:57.600 --> 00:02:16.480
tardiness. >> All right. Anyone else before we move to the back to the design consultant? All right. Uh, Fahad, I guess on your team, is there anyone else on the design consultant side?

9
00:02:16.480 --> 00:02:34.800
It's just myself and Adam Cross today. >> Okay, perfect. And then uh we also have the the contractor from RevCon. Can you introduce yourself starting Jim? >> Yeah, Jim Schuman with RevCon. I am the

10
00:02:34.800 --> 00:02:51.360
project manager uh for this project here. >> Anyone else you want to introduce? >> Uh I'm Agular. I'm also with Revcon. I I'll be doing the safety and the environmental for this project. >> Thank you.

11
00:02:51.360 --> 00:03:08.239
>> Uh this is Albert Martinez with Revcon. I was the estimator for this project. >> Perfect. >> All right. Um now that we have our introductions completed. Uh so we're going to go through the uh purpose of

12
00:03:08.239 --> 00:03:23.440
this meeting is to provide information about the Northtown Tan Parkway and Beach Street project. This meeting will include the project location, projects purpose and scope, construction progress, process, project

13
00:03:23.440 --> 00:03:39.519
schedule, not and notification. All questions will be answered at the end of the presentation. So, an overall view of the project location. It's North Tarant Parkway and North Beach.

14
00:03:39.519 --> 00:03:58.080
It's bounded by 35 West Loop 820 and Main Street looking big picture. So the project purpose is to enhance safety, mobility, operational efficiency at North Tan

15
00:03:58.080 --> 00:04:17.040
Parkway and North Beach Street intersection by improving capacity, optimizing turning movements, and upgrading illumination. So, the project scope includes additional concrete on the left and right turn lanes, channelizing right

16
00:04:17.040 --> 00:04:35.240
turn islands, upgraded traffic signals, pedestrian sidewalk and curb ramps, drainage, illumination, signage, pavement markings, and necessary utility adjustments.

17
00:04:36.000 --> 00:04:51.360
So here is the here are the plans. So we have uh traffic signal replacement on all four corners along with pedestrian sidewalk and curb ramps. We have the

18
00:04:51.360 --> 00:05:13.680
dedicated left turn lanes on all four approaches. We also have dedicated right turn lane improvements and pavement marking improvements. The construction process is as follows. We'll go with notification,

19
00:05:13.680 --> 00:05:29.759
traffic control implementation, erosion control plan implementation, site clearing and demolition. Then we'll go through the phased construction process which will have total of eight phases.

20
00:05:29.759 --> 00:05:46.720
traffic control and erosion control removal then final cleanup. So the project schedule and notification the anticipated project start will be August 24th, 2026.

21
00:05:46.720 --> 00:06:03.919
Project duration is 390 calendar days. The anticipated project completion will be October of 2027. So working hours will be standard

22
00:06:03.919 --> 00:06:20.800
7 to 6 p.m. Monday through Friday and then if requested in writing there will be weekend hours of 9 to 5. the project notification. There will be project signs placed seven days before

23
00:06:20.800 --> 00:06:36.400
construction and then there will be notices to residents and businesses 7 days before construction via door hangers. The project schedule could be affected by unforeseen events such as inclement

24
00:06:36.400 --> 00:06:54.400
weather. So, we'll go through some frequently asked questions. Question, will the intersection or roadway bay be completely closed? Answer, no. Full intersection or roadway

25
00:06:54.400 --> 00:07:16.800
closures are currently anticipated. Temporary lane closures and traffic shifts may be required during certain construction activities. Advanced warning signs will be provided. Will utility service be interrupted?

26
00:07:16.800 --> 00:07:37.280
Utility adjustments will be required. However, no plan interruptions to water, electricity, communications or other services are to expected. Are we impacting driveways in the project? If so, will there be any access

27
00:07:37.280 --> 00:07:53.199
to the property during driveway construction? There will be multiple driveway reconstructions in this project. We will be replacing the driveways half at a time and will provide continuous

28
00:07:53.199 --> 00:08:11.120
access to the properties at all times. Question will existing irrigation systems or grass be impacted in this project? Answer: If an existing irrigation system or grass parkway is impacted by the

29
00:08:11.120 --> 00:08:27.199
construction, the contractor will be required to repair these to preconstruct pre-construction conditions. If an irrigation system within the limits of the proposed improvements, the system will be adjusted by the

30
00:08:27.199 --> 00:08:47.040
contractor. Question, how will construction noise, dust, and debris be controlled? Answer: The contractor will be required to follow city requirements for working hours, dust control, site maintenance,

31
00:08:47.040 --> 00:09:04.880
and debris removal. The contractor will also maintain traffic control devices and secure the work area outside of working hours. Question. What happens if construction encounters unexpected conditions?

32
00:09:04.880 --> 00:09:22.160
Answer: unexpected utilities, weather, material availability, or field conditions could affect the schedule. The city will provide schedule updates when significant changes occur. All right. Uh that is the end of our

33
00:09:22.160 --> 00:09:38.519
presentation. Uh here are some contact information. Uh my program manager Chad Allen, myself, uh Rodrik Baker, who is the city inspector, and then um Jim Schuman from Revcon.

34
00:09:39.920 --> 00:10:14.839
Now we have some time for some questions. So, I'm going to open up the the floor so people can ask some questions. Uh, go ahead and unmute if or raise your hands if you're asking some questions.

35
00:10:18.160 --> 00:10:34.560
All right. So, our first question is from Christina. Is this the same project that was to be done a few years ago? So, this is a 2022 bond project.

36
00:10:34.560 --> 00:10:55.360
However, due to right-of-way uh delays, we are now starting the project. All right, Booker T. Have we already identified the homes with driveways to be a affected?

37
00:10:55.360 --> 00:11:16.720
There are no homes affected. Only I'll go ahead and uh pull up the plans. I'm going to hand the screen to you. >> Yeah. Do you want me to answer that, Philip? I can yeah maybe shed some light on that. >> Um so there are no homes uh with

38
00:11:16.720 --> 00:11:33.040
driveways that will be affected but I can share a traffic control plan um that will show the overall layout and the the driveways that are being affected. Um let me know if you can see my screen. I guess I should confirm first. >> I can see your screen.

39
00:11:33.040 --> 00:11:48.399
>> Perfect. >> So the fe so the driveways that are affected are all commercial driveways on this intersection. Again, the improvements are within just the the approaches for the intersection. Um, and as Philip showed earlier, the the scope includes dual left turn lanes, right

40
00:11:48.399 --> 00:12:04.240
turn channelized right turn lanes, signal improvements, and then curb ramp improvements that go hand inhand with that at the intersection itself. Um, so there will be, to answer your question, no homes that with driveways that will be affected. >> Uh, roger that. Thank you. I

41
00:12:04.240 --> 00:12:22.000
misunderstood. I >> I guess every meeting has to have their own their one token stupid question. So, I'll take that spot. >> Oh, no, no, it was a valid question, so I'm glad you asked it. >> Thank you all so much, gentlemen. >> No problem.

42
00:12:22.000 --> 00:12:47.680
Does anyone else have any questions? You can raise your uh does any Let's see if anyone raised their hands. I don't see any raised hands. Th >> This is Matt. I joined late. Is this a Is this a set of documents that you guys

43
00:12:47.680 --> 00:13:11.920
could send out for review? >> Chad, can you answer this one for me? >> I don't know what's typically done here. >> Uh, yes. We can definitely send out this presentation um to the public. No problem. We can also ask Laura to post it on the city's web page for the

44
00:13:11.920 --> 00:13:28.320
project. But if you'll put your email in the chat, we can definitely email this presentation to you. >> Very good. Thank you. >> So, okay. So, Matt, if you join late, this is a preconstruction community meeting for this project. So, basically, the plans are done. We've hired a

45
00:13:28.320 --> 00:13:44.160
contractor and we're ready to start construction. So, that's what this meeting was about. But yeah, we can definitely send you this presentation. >> What is the timing for construction? >> Philip, can you give um can you scroll to the schedule page? Didn't we have a

46
00:13:44.160 --> 00:14:00.880
schedule page? >> Can you hand back control of the screen? >> Yes. I have stopped sharing. See where's the share? Okay, there you go. >> I'm sorry if you guys already went through that.

47
00:14:00.880 --> 00:14:16.399
>> That's okay. No problem. That's a pretty common question that people want to know. >> Pretty common question. This is one of our biggest and most complicated intersection projects from the 2022 bond program. We did have to condemn to get some right away to in order to build

48
00:14:16.399 --> 00:14:33.120
this project and condemnation does take a long time. It's a very long process. So, it has taken us a while to get to this point, but we're very excited to know that construction is about to start for this project. So, um, Philip, if you can, um, share the schedule page, that would be awesome.

49
00:14:33.120 --> 00:14:52.600
>> Uh, can you see the schedule page? >> I cannot I don't >> ask. This is Matt. I can't see it. >> Yeah. >> Let me try one more time. Let's see. Screen two.

50
00:14:53.600 --> 00:15:08.399
>> Okay. Can you see it now? >> Yes. >> Yes, sir. >> Thank you. Okay. So, um the anticipated uh project start is August 24th, 2026 and then the uh project duration is 390

51
00:15:08.399 --> 00:15:32.760
calendar days and anticipated project completion is October 2027. >> Okay, let's see. Me open up the chat. It looks like there were a couple more questions. Okay.

52
00:15:37.839 --> 00:15:56.880
All right. So, I guess Dro Roberts asked, "Are all four dedicated right turn lanes going to have an island or just a dedicated turn lane?" And then um I'll refer I'll give that to

53
00:15:56.880 --> 00:16:12.320
Bahad to answer. >> Yes, they will all have a an island. And Philip, I don't know if it's possible for you to share that overview. Um that might help convey a pretty good picture of what the the dedicated right turn lanes and then the channelized islands

54
00:16:12.320 --> 00:16:27.279
look like. Um if not, I can pull it up on my end as well. I think it was >> Okay, I'm my screen right now. So, uh you're talking about the pork chops, right? >> Correct. Yeah. So, all four intersections will have that. Yes.

55
00:16:27.279 --> 00:16:43.040
>> The protected uh right turn. >> And then I think there's a follow-up question or another question about the two left turn lanes. Uh so I'll take that too if that's okay and answer that. Um there will be plenty of room for those dual left turn lanes and there

56
00:16:43.040 --> 00:17:04.000
will be refreshed pavement markings. Uh it's a little hard to see on that, but there are puppy tracks in the middle of that intersection um to help motorists navigate through uh that intersection. >> I think what he's saying is the current

57
00:17:04.000 --> 00:17:21.280
turn uh the current lanes without extra space looks tight, but we're building additional lanes. >> Correct. Yes, exactly. So, there will be additional pavement and and essentially uh more concrete added on to widen that intersection and allow for that um for

58
00:17:21.280 --> 00:17:40.799
dual lift turn lanes on all approaches. Okay. And so Matt asks for um send the plans to his email. Let's see what else. DH which contractor has been selected for

59
00:17:40.799 --> 00:17:56.000
this project. Are there liquidated damages going to be assessed if the end of the date if the end date is exceeded? So Revcon is the

60
00:17:56.000 --> 00:18:13.120
see if I say it anywhere. Revcon is the contractor selected and uh as part of the contract documents there are uh LDS. Okay. Um Craig Charton

61
00:18:13.120 --> 00:18:28.320
I missed what condemnation was required for this project. Would you please repeat that? So, um condemnation was required for the southwest corner and um that

62
00:18:28.320 --> 00:18:44.960
condemnation has been completed and that's why we're starting this project. All right. Thank you for clearing up about the left turn lanes and thank you. Okay, any uh further questions?

63
00:18:44.960 --> 00:19:00.799
can raise your hand if you would like and I will try to address that or type it in the All right. Uh James Petty >> uh yes I was wondering about the there's

64
00:19:00.799 --> 00:19:21.120
a lot of key utility poles in nearby that intersection or are those just going to get moved or are they going to be buried? I can go ahead and answer some of that too, Philip, and uh you can chime in if there's something that I leave off. But

65
00:19:21.120 --> 00:19:36.400
to answer your question, there are utility poles that are getting relocated. Not all of that is going to be underground. There will be some overhead utilities still when the when the project is finished. Most of those poles have been relocated, but there are a couple that are still pending. Uh and

66
00:19:36.400 --> 00:19:50.640
that's that's because there is existing signal infrastructure uh in particular on one of those poles. So um that will get moved as the construction progresses and the new signal infrastructure is up and we are ready to transfer uh from the

67
00:19:50.640 --> 00:20:10.000
old signal to the new signal. >> Gotcha. >> That's perfect. >> And I had a followup on the the other guy who was asking about the condemnation. Um what exactly on the southwest corner was condemned? It was a piece of ground or a building or what

68
00:20:10.000 --> 00:20:39.159
exactly? It's whatever the uh right turn lane was encroaching into and then now it's not because we we have uh acquired that that land. >> Okay, gotcha. >> Anyone else uh have any questions?

69
00:20:53.760 --> 00:21:10.799
All right. Um well if not thank you all for attending this meeting and I will um well Laura will post the presentation but I can also uh send it to everyone. Thank you very much for attending this

70
00:21:10.799 --> 00:21:19.799
meeting. >> Thank you. Thanks very much. >> Thank you.